Based on the Figure 6.4,6.5 and 6.6 What are the benefits and decisions Project managers can take? Note: The answer should be based on the information in the picture and your own work.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Q : Based on the Figure 6.4,6.5 and 6.6 What are the benefits and decisions Project managers can take? Note: The answer should be based on the information in the picture and your own work.
ACTIVITY PLAN
Delverables
Measurels) of accompishment
Key constrants and assumptons
.
ESTIMATED
RESOURCES
BAME DIATE
PREDECESSO
TASKS
ESTIMATED
TIME
DURATIONS)
TASKS
ASSIGNED TO
FIGURE 6.4 A form to assist hierarchical planning.
The Work Breakdown Structure
Using this hierarchical planning process results in a work breakdown structure known as a
WBS. The WBS is the main tool for managing the project scope as described in PMBOK.
The WBS is not one thing. It can take a wide variety of forms that, in turn, serve a wide
variety of purposes. In many ways, the WBS is a simplified form of the project plan focused
on the actual tasks of the project. It often shows the organizational elements associated
with a project subdivided into hierarchical units of tasks, subtasks, work packages, etc.
Figure 6.5 is such a WBS for a conference. The Food group in the Facilities staff has
responsibility for meals and drinks, including coffee breaks and water pitchers in the
conference rooms. Five different food functions are shown, each presumably broken down
into more detailed tasks. In this case, the account numbers for each task are shown so that
proper charges can be assigned for each piece of work done on the project.
Professor Andrew Vazsonyi has called this type of diagram a Gozinto chart, after the
famous Italian mathematician Prof. Zepartzat Gozinto (of Vazsonyi's invention). Readers
will recognize the parallel to the basic organizational chart depicting the formal structure of
an organization, or the Bill of Materials in a Materials Requirements Planning (MRP) system.
Another form of the WBS is an outline with the top organizational (Level 1) tasks on the left
and successive levels appropriately indented. Most current project management software will
generate a WBS on command. Microsoft's Project", for example, links the indented activity
levels with a Gantt chart that visually shows the activity durations at any level.
In general, the WBS is an important document and can be tailored for use in a number
of different ways. It may illustrate how each piece of the project contributes to the whole in
terms of performance, responsibility, budget, and schedule. It may, if the PM wishes, list
the vendors or subcontractors associated with specific tasks. It may be used to document
that all parties have signed off on their various commitments to the project. It may note
detailed specifications for any work package, establish account numbers, specify hardware/
software to be used, and identify resource needs. It may serve as the basis for making cost
estimates or estimates of task duration. Largely, the WBS is a planning tool, but it may also
be used as an aid in monitoring and controlling projects. Again. it is important to remember
PMBOK
5.4
Leveis
Careeson
Frtertuonvet
Lecatan
Paite
(12.00.000
Smsione
(1400.00
(15.00.d
Tes
Rates
Ses
Dutes
Fend
Budng
Home
1.00 (1.2.0 (1201 c0 (12.00.00 (12m0)
Types
Pap
Pan
Local
Cattee
braa
12.02.01)
Bretast
12.02.00)
Lundhes
Dasers
(12.00.04
Drnks
(12 2 05
FIGURE S.S Work hreakdowe stracture (account sumbers shown).
that no single WBS contains all of the elements described and any given WBS shouald be
designed with specific uses in mind. Its uses are limited only by the needs of the project and
the imagination of the PM. No one version of the WBS will sauit all needs, so the WBS is
not a document, but any given WBS is simply one of many passible documents.
However, in constructing the WBS, all work package information should be reviewed
with the individals or organizations who have responsibility for doing or supporting the
wurk in onder to verify the WBS's accuracy. Resource requirements, schedules, and subtask
relationships can now be aggregated to form the next higher level of the WBS, continuing on
to each succeeding level of the hierarchy. At the uppermost level, we have a summary of the
project, its budget, and an estimate of the duration of each work element. For the moment,
we are ignoring uncertainty in estimating the budget and duration af work elements.
As we noted, the actual form the WBS takes is not sacrosanct. Figure 6.6 shows a
partial WBS for a college "Cureer Day." which includes the activities, who is respon-
sible, the time each task is expected to take, which tasks must precede each task, and
any external resources needed for that task. However, not all elements of the WBS shown
in Figure 6.6 may be needed in other cases. In some cases, for example, the amoants of
specific resources required may not be relevant. In others, "due dates" may be substituted
for activity durations. The appearance of a WBS will probably differ in different organiza-
tions. In some plans, numbers may be used to identify activities; in others, letters. In still
others, combinations of letters and numbers may be used. An example of a WBS t0 acquire
a subsidiary is illustrated in Figures 6.7a and 6.7b. A verbal "WBS" was written in the form
of a memorandum, Figure 6.7a, and was followed by the more common, tabular plan shown
in Figure 6.7b. Only one page of a five-page plan is shown. The individuals and groups
mentioned developed similar plans at a greater level of detail. (Names have been changed
at the request of the firm.)
Transcribed Image Text:ACTIVITY PLAN Delverables Measurels) of accompishment Key constrants and assumptons . ESTIMATED RESOURCES BAME DIATE PREDECESSO TASKS ESTIMATED TIME DURATIONS) TASKS ASSIGNED TO FIGURE 6.4 A form to assist hierarchical planning. The Work Breakdown Structure Using this hierarchical planning process results in a work breakdown structure known as a WBS. The WBS is the main tool for managing the project scope as described in PMBOK. The WBS is not one thing. It can take a wide variety of forms that, in turn, serve a wide variety of purposes. In many ways, the WBS is a simplified form of the project plan focused on the actual tasks of the project. It often shows the organizational elements associated with a project subdivided into hierarchical units of tasks, subtasks, work packages, etc. Figure 6.5 is such a WBS for a conference. The Food group in the Facilities staff has responsibility for meals and drinks, including coffee breaks and water pitchers in the conference rooms. Five different food functions are shown, each presumably broken down into more detailed tasks. In this case, the account numbers for each task are shown so that proper charges can be assigned for each piece of work done on the project. Professor Andrew Vazsonyi has called this type of diagram a Gozinto chart, after the famous Italian mathematician Prof. Zepartzat Gozinto (of Vazsonyi's invention). Readers will recognize the parallel to the basic organizational chart depicting the formal structure of an organization, or the Bill of Materials in a Materials Requirements Planning (MRP) system. Another form of the WBS is an outline with the top organizational (Level 1) tasks on the left and successive levels appropriately indented. Most current project management software will generate a WBS on command. Microsoft's Project", for example, links the indented activity levels with a Gantt chart that visually shows the activity durations at any level. In general, the WBS is an important document and can be tailored for use in a number of different ways. It may illustrate how each piece of the project contributes to the whole in terms of performance, responsibility, budget, and schedule. It may, if the PM wishes, list the vendors or subcontractors associated with specific tasks. It may be used to document that all parties have signed off on their various commitments to the project. It may note detailed specifications for any work package, establish account numbers, specify hardware/ software to be used, and identify resource needs. It may serve as the basis for making cost estimates or estimates of task duration. Largely, the WBS is a planning tool, but it may also be used as an aid in monitoring and controlling projects. Again. it is important to remember PMBOK 5.4 Leveis Careeson Frtertuonvet Lecatan Paite (12.00.000 Smsione (1400.00 (15.00.d Tes Rates Ses Dutes Fend Budng Home 1.00 (1.2.0 (1201 c0 (12.00.00 (12m0) Types Pap Pan Local Cattee braa 12.02.01) Bretast 12.02.00) Lundhes Dasers (12.00.04 Drnks (12 2 05 FIGURE S.S Work hreakdowe stracture (account sumbers shown). that no single WBS contains all of the elements described and any given WBS shouald be designed with specific uses in mind. Its uses are limited only by the needs of the project and the imagination of the PM. No one version of the WBS will sauit all needs, so the WBS is not a document, but any given WBS is simply one of many passible documents. However, in constructing the WBS, all work package information should be reviewed with the individals or organizations who have responsibility for doing or supporting the wurk in onder to verify the WBS's accuracy. Resource requirements, schedules, and subtask relationships can now be aggregated to form the next higher level of the WBS, continuing on to each succeeding level of the hierarchy. At the uppermost level, we have a summary of the project, its budget, and an estimate of the duration of each work element. For the moment, we are ignoring uncertainty in estimating the budget and duration af work elements. As we noted, the actual form the WBS takes is not sacrosanct. Figure 6.6 shows a partial WBS for a college "Cureer Day." which includes the activities, who is respon- sible, the time each task is expected to take, which tasks must precede each task, and any external resources needed for that task. However, not all elements of the WBS shown in Figure 6.6 may be needed in other cases. In some cases, for example, the amoants of specific resources required may not be relevant. In others, "due dates" may be substituted for activity durations. The appearance of a WBS will probably differ in different organiza- tions. In some plans, numbers may be used to identify activities; in others, letters. In still others, combinations of letters and numbers may be used. An example of a WBS t0 acquire a subsidiary is illustrated in Figures 6.7a and 6.7b. A verbal "WBS" was written in the form of a memorandum, Figure 6.7a, and was followed by the more common, tabular plan shown in Figure 6.7b. Only one page of a five-page plan is shown. The individuals and groups mentioned developed similar plans at a greater level of detail. (Names have been changed at the request of the firm.)
WBS
Career Day
Time
Steps
Responsibility
(weeks)
Prec.
Resources
1. Contact Organizations
a. Print forms
Secrelary
6.
Print shop
b. Contact organizations
Program manager
Word processing
15
1.a
c. Collect display information
Olice manager
4
1.b
d. Gather college particulars
Secretary
4
1.b
c. Print programs
Secretary
1.d
Print shop
f. Print participants' certificates
Graduate assistant
8
Print shop
2. Banquet and Refreshments
a. Select guest speaker
Program manager
14
b. Organize food
Program manager
1.b
Caterer
c. Organize liquor
Director
10
1.6
Dept. of Liquor Control
d. Organize refreshments
Graduate assistant
1.b
Purchasing
3. Publicity and Promotion
a. Send invitations
Graduate assistant
Word processing
b. Organize gift certificates
Graduate assistant
5.5
c. Arrange banner
Graduate assistant
Print shop
5
1.d
d. Contact faculty
Program manager
1.5
1.d
Word processing
e. Advertise in college paper
Secretary
5
I.d
Newspaper
f. Class announcements
Graduate assistant
1
3.d
Registrar's officc
g. Organize posters
Secretary
4.5
1.d
Print shop
4. Facilities
a. Arrange facility for event
Program manager
2.5
1.c
b. Transport materials
Office manager
.5
4.a
Movers
FIGURE 6.6 Partial WBS for college "Career Day."
Occasionally, planners attempt to plan by using “Gantt charts," a network device com-
monly used to display project schedules (see Figure 6.8). The Gantt chart was invented as
a scheduling aid. In essence, the project's activities are shown on a horizontal bar chart
with the horizontal bar lengths proportional to the activity durations. The activity bars
are connected to predecessor and successor activities with arrows. The project schedule
integrates the many different schedules relevant to the various parts of the project. It is
comprehensive and may include contractual commitments, key interfaces and sequencing,
milestone events, and progress reports. In addition, a time contingency reserve for
Transcribed Image Text:WBS Career Day Time Steps Responsibility (weeks) Prec. Resources 1. Contact Organizations a. Print forms Secrelary 6. Print shop b. Contact organizations Program manager Word processing 15 1.a c. Collect display information Olice manager 4 1.b d. Gather college particulars Secretary 4 1.b c. Print programs Secretary 1.d Print shop f. Print participants' certificates Graduate assistant 8 Print shop 2. Banquet and Refreshments a. Select guest speaker Program manager 14 b. Organize food Program manager 1.b Caterer c. Organize liquor Director 10 1.6 Dept. of Liquor Control d. Organize refreshments Graduate assistant 1.b Purchasing 3. Publicity and Promotion a. Send invitations Graduate assistant Word processing b. Organize gift certificates Graduate assistant 5.5 c. Arrange banner Graduate assistant Print shop 5 1.d d. Contact faculty Program manager 1.5 1.d Word processing e. Advertise in college paper Secretary 5 I.d Newspaper f. Class announcements Graduate assistant 1 3.d Registrar's officc g. Organize posters Secretary 4.5 1.d Print shop 4. Facilities a. Arrange facility for event Program manager 2.5 1.c b. Transport materials Office manager .5 4.a Movers FIGURE 6.6 Partial WBS for college "Career Day." Occasionally, planners attempt to plan by using “Gantt charts," a network device com- monly used to display project schedules (see Figure 6.8). The Gantt chart was invented as a scheduling aid. In essence, the project's activities are shown on a horizontal bar chart with the horizontal bar lengths proportional to the activity durations. The activity bars are connected to predecessor and successor activities with arrows. The project schedule integrates the many different schedules relevant to the various parts of the project. It is comprehensive and may include contractual commitments, key interfaces and sequencing, milestone events, and progress reports. In addition, a time contingency reserve for
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.