Question

The question in the two pictures.

You are the project manager on a software development project that has $800,000 for
the budget. There are two teams of programmers that will work for six months for a
total of 10,000 hours. According to the project schedule your team should be done
with 38% of the work which planned to cost 38% of the budget. As of today, the
project is 40% complete while 50% of the budget has been used.
From the given information determine the following and then answer the question
below.
Answers:
BAC =
PV=
AC =
EV =
CV =
SV=
CPI =
SPI =
How is the project doing?
Is it ahead of schedule or behind schedule and Why?
Is it under budget or over budget and Why?
Transcribed Image Text:You are the project manager on a software development project that has $800,000 for the budget. There are two teams of programmers that will work for six months for a total of 10,000 hours. According to the project schedule your team should be done with 38% of the work which planned to cost 38% of the budget. As of today, the project is 40% complete while 50% of the budget has been used. From the given information determine the following and then answer the question below. Answers: BAC = PV= AC = EV = CV = SV= CPI = SPI = How is the project doing? Is it ahead of schedule or behind schedule and Why? Is it under budget or over budget and Why?
Question 2.1:
Question 2.2
How do functionality, features, system outputs, performance, reliability, and
maintainability requirements affect quality planning? Explain each scope aspect and
then explain how determining these aspects affect quality planning.
Create a Pareto chart based on the information in the following table. First create a
spreadsheet in Excel using the data in the table. List the most frequently requested
program first. Use the Excel template called pareto_chart.xls. Your resulting chart
should look similar to the one explained in class in Figure 8-7. Explain your chart to
determine which programs should focus on providing.
Provide one example for a requirement for the project you are working on and
determine under which scope aspect it falls.
Answer:
Customer Request
Number of Requests
Walking program
64
Volleyball program
20
Weight reduction class
80
Stop smoking class
16
Answer:
Transcribed Image Text:Question 2.1: Question 2.2 How do functionality, features, system outputs, performance, reliability, and maintainability requirements affect quality planning? Explain each scope aspect and then explain how determining these aspects affect quality planning. Create a Pareto chart based on the information in the following table. First create a spreadsheet in Excel using the data in the table. List the most frequently requested program first. Use the Excel template called pareto_chart.xls. Your resulting chart should look similar to the one explained in class in Figure 8-7. Explain your chart to determine which programs should focus on providing. Provide one example for a requirement for the project you are working on and determine under which scope aspect it falls. Answer: Customer Request Number of Requests Walking program 64 Volleyball program 20 Weight reduction class 80 Stop smoking class 16 Answer:
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.