b) A 4-hour rain of an amount of 1 cm (i.e intensity of 1/4 cm/hr) falls over a catchment shown in Figure 1.1. The time of concentration from the lines AA, BB, CC and DD are 1, 2, 3 and 4 hours, respectively, to the site 0 where the discharge measurements are made. i. ji. iii. Isochrones Catchment area IV (1) M4 50 ha 40 ha 30 ha 20 ha Basin boundary Discharge Figure 1.1 Determine the flow hydrograph at site 0 using the time-area curve method for this 4-hr rain with an intensity distribution given by: Time (hr) 1 2 3 Rainfall intensity 1/4 1/4 1/4 (cm/hr) Verify that the resulting flow hydrograph represents a unit hydrograph of 4-hr rain in the catchment Use this unit hydrograph to obtain flow hydrograph in the catchment for the following net rainfall profile Time (hr) Net rainfall (cm) 0-4 4-8 2 4 4 1/4

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
b) A 4-hour rain of an amount of 1 cm (i.e intensity of 1/4 cm/hr) falls over a
catchment shown in Figure 1.1. The time of concentration from the lines AA,
BB, CC and DD are 1, 2, 3 and 4 hours, respectively, to the site 0 where
the discharge measurements are made.
i.
ji.
iii.
Isochrones
Catchment
area
IV
(1)
M4
50 ha
40 ha
30 ha
20 ha
Basin
boundary
Discharge
Figure 1.1
Determine the flow hydrograph at site 0 using the time-area
curve method for this 4-hr rain with an intensity distribution
given by:
Time (hr)
1 2 3
Rainfall intensity 1/4 1/4 1/4
(cm/hr)
Verify that the resulting flow hydrograph represents a unit
hydrograph of 4-hr rain in the catchment
Use this unit hydrograph to obtain flow hydrograph in the
catchment for the following net rainfall profile
Time (hr)
Net rainfall (cm)
0-4 4-8
2 4
4
1/4
Transcribed Image Text:b) A 4-hour rain of an amount of 1 cm (i.e intensity of 1/4 cm/hr) falls over a catchment shown in Figure 1.1. The time of concentration from the lines AA, BB, CC and DD are 1, 2, 3 and 4 hours, respectively, to the site 0 where the discharge measurements are made. i. ji. iii. Isochrones Catchment area IV (1) M4 50 ha 40 ha 30 ha 20 ha Basin boundary Discharge Figure 1.1 Determine the flow hydrograph at site 0 using the time-area curve method for this 4-hr rain with an intensity distribution given by: Time (hr) 1 2 3 Rainfall intensity 1/4 1/4 1/4 (cm/hr) Verify that the resulting flow hydrograph represents a unit hydrograph of 4-hr rain in the catchment Use this unit hydrograph to obtain flow hydrograph in the catchment for the following net rainfall profile Time (hr) Net rainfall (cm) 0-4 4-8 2 4 4 1/4
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
steps

Unlock instant AI solutions

Tap the button
to generate a solution

Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning