Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your company's database indicates that developers can handle eight function points each person-month and that the cost p developer at your firm is $5,800 per month. You and your team of five developers have come up with the following requirements: (Round your "Estimated duration" answer to 2 decimal places.) Elements Inputs Outputs Inquiries Files Interfaces Count 14 8 8 32 22 Complexity Low Low High Medium High Calculate the total number of function points and the estimated cost and duration of the Tidal project? (Use "complexity weighting"). Estimated total number of function points Estimated cost

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Aa 49.

Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the
project. Your company's database indicates that developers can handle eight function points each person-month and that the cost p
developer at your firm is $5,800 per month. You and your team of five developers have come up with the following requirements:
(Round your "Estimated duration" answer to 2 decimal places.)
Elements
Inputs
Outputs
Inquiries
Files
Interfaces
Count
14
8
8
32
22
Complexity
Low
Low
High
Medium
High
Calculate the total number of function points and the estimated cost and duration of the Tidal project? (Use "complexity weighting").
Estimated total number of function points
Estimated cost
Estimated duration
months
Transcribed Image Text:Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your company's database indicates that developers can handle eight function points each person-month and that the cost p developer at your firm is $5,800 per month. You and your team of five developers have come up with the following requirements: (Round your "Estimated duration" answer to 2 decimal places.) Elements Inputs Outputs Inquiries Files Interfaces Count 14 8 8 32 22 Complexity Low Low High Medium High Calculate the total number of function points and the estimated cost and duration of the Tidal project? (Use "complexity weighting"). Estimated total number of function points Estimated cost Estimated duration months
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman