Assume that you are the project manager for a project for enterprise system development for LLBGC. Based on preliminary joint application design activities, the tasks and resources were identified. Using the information in Table 1, draw a network diagram.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Assume that you are the project manager for a project for enterprise system development for LLBGC. Based on preliminary joint application design activities, the tasks and resources were identified. Using the information in Table 1, draw a network diagram.

### A Project Network Diagram

This diagram represents a project network, illustrating a sequence of activities necessary for project completion. The activities are depicted as nodes labeled A through F, each associated with a numerical value representing the duration or time required to complete the task.

- **Activity A**: Duration of 1 unit. This is the starting point of the project.
- **Activity B**: Duration of 3 units. It follows Activity A.
- **Activity C**: Duration of 2 units. It also follows Activity A concurrently with Activity B.
- **Activity D**: Duration of 5 units. It follows Activity B.
- **Activity E**: Duration of 2 units. It follows Activity C.
- **Activity F**: Duration of 3 units. It follows Activity D and E, indicating that both preceding tasks must be completed before starting this activity.

### Connections and Flow

- The arrows between nodes indicate the direction and dependency of tasks: which activity must be completed to initiate the subsequent activity.
- The project workflow diagram is organized in a way that allows for parallel task execution, notably from Activity A to B and C simultaneously.
- The dependencies ensure that Activities D and E converge into Activity F for project completion.

This network diagram is a crucial component for planning and managing project timelines efficiently, enabling the identification of critical paths and potential bottlenecks.
Transcribed Image Text:### A Project Network Diagram This diagram represents a project network, illustrating a sequence of activities necessary for project completion. The activities are depicted as nodes labeled A through F, each associated with a numerical value representing the duration or time required to complete the task. - **Activity A**: Duration of 1 unit. This is the starting point of the project. - **Activity B**: Duration of 3 units. It follows Activity A. - **Activity C**: Duration of 2 units. It also follows Activity A concurrently with Activity B. - **Activity D**: Duration of 5 units. It follows Activity B. - **Activity E**: Duration of 2 units. It follows Activity C. - **Activity F**: Duration of 3 units. It follows Activity D and E, indicating that both preceding tasks must be completed before starting this activity. ### Connections and Flow - The arrows between nodes indicate the direction and dependency of tasks: which activity must be completed to initiate the subsequent activity. - The project workflow diagram is organized in a way that allows for parallel task execution, notably from Activity A to B and C simultaneously. - The dependencies ensure that Activities D and E converge into Activity F for project completion. This network diagram is a crucial component for planning and managing project timelines efficiently, enabling the identification of critical paths and potential bottlenecks.
# Table 1: Tasks, Duration, and Predecessor

This table provides a detailed breakdown of the tasks involved in a project, including their durations and predecessors.

| Task # | Task Name                      | Duration | Predecessors  |
|--------|--------------------------------|----------|---------------|
| 1      | Organize Project               | 21 days  | -             |
| 2      | Collect Requirements           | 27 days  | 1             |
| 3      | Structure Requirements         | 34 days  | 2             |
| 4      | Analyze Processes              | 12 days  | 3             |
| 5      | Develop Conceptual Database    | 22 days  | 3             |
| 6      | Develop Logical Database       | 26 days  | 5             |
| 7      | Develop Physical Database      | 22 days  | 6             |
| 8      | Develop User Interface         | 15 days  | 6             |
| 9      | Develop Modules                | 56 days  | 7, 8          |
| 10     | Integrate Modules              | 26 days  | 9             |
| 11     | Project Cutover                | 0 days   | 10            |
| 12     | Post Cutover Activity          | 17 days  | 11            |

## Detailed Explanation:

- **Task Number (Task #):** An identifier for each task in the sequence.
- **Task Name:** Describes the activity to be performed.
- **Duration:** The time allocated to complete each task, measured in days.
- **Predecessors:** Tasks that must be completed before a particular task can begin.

The structured sequence of tasks and their dependencies helps in effective project planning and management. For example, "Develop Logical Database" can only start after "Develop Conceptual Database" is completed.
Transcribed Image Text:# Table 1: Tasks, Duration, and Predecessor This table provides a detailed breakdown of the tasks involved in a project, including their durations and predecessors. | Task # | Task Name | Duration | Predecessors | |--------|--------------------------------|----------|---------------| | 1 | Organize Project | 21 days | - | | 2 | Collect Requirements | 27 days | 1 | | 3 | Structure Requirements | 34 days | 2 | | 4 | Analyze Processes | 12 days | 3 | | 5 | Develop Conceptual Database | 22 days | 3 | | 6 | Develop Logical Database | 26 days | 5 | | 7 | Develop Physical Database | 22 days | 6 | | 8 | Develop User Interface | 15 days | 6 | | 9 | Develop Modules | 56 days | 7, 8 | | 10 | Integrate Modules | 26 days | 9 | | 11 | Project Cutover | 0 days | 10 | | 12 | Post Cutover Activity | 17 days | 11 | ## Detailed Explanation: - **Task Number (Task #):** An identifier for each task in the sequence. - **Task Name:** Describes the activity to be performed. - **Duration:** The time allocated to complete each task, measured in days. - **Predecessors:** Tasks that must be completed before a particular task can begin. The structured sequence of tasks and their dependencies helps in effective project planning and management. For example, "Develop Logical Database" can only start after "Develop Conceptual Database" is completed.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.