An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $12.6 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $15.12 million. Under Plan B, cash flows would be $2.2389 million per year for 20 years. The firm's WACC is 12.9%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For example, an answer of $10,550,000 should be entered as 10.55. If an amount is zero, enter "0". Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. Identify the IRR of Plans A & B. Round your answers to two decimal places. Find the crossover rate. Round your answers to two decimal places.
An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $12.6 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $15.12 million. Under Plan B, cash flows would be $2.2389 million per year for 20 years. The firm's WACC is 12.9%.
-
Construct
NPV profiles for Plans A and B. Enter your answers in millions. For example, an answer of $10,550,000 should be entered as 10.55. If an amount is zero, enter "0". Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. - Identify the
IRR of Plans A & B. Round your answers to two decimal places. - Find the crossover rate. Round your answers to two decimal places.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images