Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A B C D E Time (sec) 12 14 8 5 20 Immediate Predecessor A A B, C D Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line= (round your response up to the next whole number)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
**Amelio Rodriguez Computing: Assembly Line Planning for PDAs**

Amelio Rodriguez Computing seeks to establish an efficient assembly line for producing a new product, the Personal Digital Assistant (PDA). Below are the tasks involved, including task times and their immediate predecessors:

| **Task** | **Time (sec)** | **Immediate Predecessor** |
|----------|----------------|--------------------------|
| A        | 12             | -                        |
| B        | 14             | A                        |
| C        | 8              | A                        |
| D        | 5              | B, C                     |
| E        | 20             | D                        |

**Objective**

Amelio aims to produce 180 PDAs per hour.

**Questions:**

a) Calculate the cycle time for producing a PDA. *(Round your response to two decimal places)*

b) Determine the theoretical minimum number of workstations Amelio can set up on this assembly line. *(Round your response up to the next whole number)*
Transcribed Image Text:**Amelio Rodriguez Computing: Assembly Line Planning for PDAs** Amelio Rodriguez Computing seeks to establish an efficient assembly line for producing a new product, the Personal Digital Assistant (PDA). Below are the tasks involved, including task times and their immediate predecessors: | **Task** | **Time (sec)** | **Immediate Predecessor** | |----------|----------------|--------------------------| | A | 12 | - | | B | 14 | A | | C | 8 | A | | D | 5 | B, C | | E | 20 | D | **Objective** Amelio aims to produce 180 PDAs per hour. **Questions:** a) Calculate the cycle time for producing a PDA. *(Round your response to two decimal places)* b) Determine the theoretical minimum number of workstations Amelio can set up on this assembly line. *(Round your response up to the next whole number)*
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.