Advise Diego Toh on the following: (a) Explain the ways in which a contract may come to an end.
On 11 August 2020, Vanya Ho entered into a contract with Diego Toh to renovate her school, The Umbrella Learning Centre and to set up the internet system for the school's online lessons starting in October. They agreed to the total sum of $100,000 with a 10% deposit of $10,000 to be paid on the signing of the contract. $20,0000 was to be paid upon the design being approved by Vanya Ho. The balance of $70,000 was to be paid on the completion of the renovation works. The contract provided that Diego Toh was to complete the renovation works and handover the school to Vanya Ho not later than 20 September 2020.
The design was approved by Vanya Ho on 18 August 2020. Diego Toh proceeded with the renovation which was completed on 19 September 2020. Vanya inspected the renovation work on 20 September 2020. She was not pleased with the internet system when she tested the wifi connection. The wifi signals were weak and created issues for running the online lessons. Diego Toh explained that his electricians have gone back to Malaysia and would only be back early 2021. He insisted that the renovation works including the setting up of the internet system were in accordance with the design as approved by Vanya.
On 21 September, Vanya Ho called an independent electrician, Klaus Soh, to inspect and advise on internet system. Klaus Soh explained that the internet system was poorly set-up. He quoted $2,000 to rectify the defects which could be completed by 25 September 2020.
On 22 September, Diego Toh contacted Vanya Ho and demanded payment of the balance amount of $70,000. Vanya Ho refused to pay the balance and insisted that Diego Toh rectify the internet system by 26 September 2020.
Advise Diego Toh on the following:
(a) Explain the ways in which a contract may come to an end.