Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please answer the question showing the complete diagram as asked in the question
![First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are
reviewing the Gantt chart at the end of day 4.
Job D was scheduled to begin early on day 2 and take 5.5 days. As of now (the review point after
day 4), it is 2 days ahead of schedule.
Job E should begin on day 1 and take 5 days. It was on time.
Job F was to begin on day 3, but maintenance forced a delay of 1.0 day. The job should now
take 5 full days. It is now on schedule.
Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to
complete.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings
have been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected
finish on top of (overlapping) the maroon dashed line provided just above the job number for each
of the tasks.
Job 1 2 3 4 5 6 7 8 9 10 11
D
E
F
Day
G
A
Now
i](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F7ed47c9a-a211-4874-a3c6-250d9d319765%2Ff4d09b85-e2a1-47a9-bb3e-262c9a4ff0d8%2Fr85mwd8_processed.png&w=3840&q=75)
Transcribed Image Text:First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are
reviewing the Gantt chart at the end of day 4.
Job D was scheduled to begin early on day 2 and take 5.5 days. As of now (the review point after
day 4), it is 2 days ahead of schedule.
Job E should begin on day 1 and take 5 days. It was on time.
Job F was to begin on day 3, but maintenance forced a delay of 1.0 day. The job should now
take 5 full days. It is now on schedule.
Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to
complete.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings
have been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected
finish on top of (overlapping) the maroon dashed line provided just above the job number for each
of the tasks.
Job 1 2 3 4 5 6 7 8 9 10 11
D
E
F
Day
G
A
Now
i
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.