Activity List for a Reroofing Project Activity Description 1 Mobilize 2 Set up scaffolding 3 Construct security barricades 4 Strip off old roofing 5 Repair damaged decking 6 Repair damaged cant strip 7 Replace sheet metal 8 Install felt roofing Duration Days 1 2 1 3 2 1 1 1 Predecessors 1 2 SS/1 2,3 4 SS/1 4,5 5 SS/1 6,7

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Activity List for a Reroofing Project
Activity Description
1 Mobilize
2 Set up scaffolding
3 Construct security barricades
4 Strip off old roofing
5 Repair damaged decking
6 Repair damaged cant strip
7 Replace sheet metal
8 Install felt roofing
9 Hot mop roof
10 Inspect roofing
11 Call for inspection
12 Remove scaffolding
13 Haul off roofing materials
14 Demobilize
Duration Days
Using the activity list provided above:
Draw a precedence diagram
1
2
1
3
2
1
1
1
2
1
1
2
2
1
*Under Predecessors, the following notation is used:
x/#: Activity x must finish # days before this activity can begin.
xSS/#: The # of days after activity x starts that this activity can begin.
xFF/#: This activity cannot finish until # days after x is completed.
XSF/#: This activity must finish # days before x can start.
Predecessors
1
2 SS/1
2,3
4 SS/1
4,5
5 SS/1
6,7
8
9
10 SF/3
10
6,7
12 FF/1, 13 FF/1
Transcribed Image Text:Activity List for a Reroofing Project Activity Description 1 Mobilize 2 Set up scaffolding 3 Construct security barricades 4 Strip off old roofing 5 Repair damaged decking 6 Repair damaged cant strip 7 Replace sheet metal 8 Install felt roofing 9 Hot mop roof 10 Inspect roofing 11 Call for inspection 12 Remove scaffolding 13 Haul off roofing materials 14 Demobilize Duration Days Using the activity list provided above: Draw a precedence diagram 1 2 1 3 2 1 1 1 2 1 1 2 2 1 *Under Predecessors, the following notation is used: x/#: Activity x must finish # days before this activity can begin. xSS/#: The # of days after activity x starts that this activity can begin. xFF/#: This activity cannot finish until # days after x is completed. XSF/#: This activity must finish # days before x can start. Predecessors 1 2 SS/1 2,3 4 SS/1 4,5 5 SS/1 6,7 8 9 10 SF/3 10 6,7 12 FF/1, 13 FF/1
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Material selection
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning