Activity Activity Description Time (Days) Prepare preliminary set of questions for the verbal section Prepare preliminary set of questions for the quantitative section Prepare preliminary set of questions for the data analysis section Search for printers who could print the test papers | Choose the test centres Print the application forms A 15 B 20 20 D 21 E 30 F 14 G Advertise the programme, sell application forms and receive filled forms from applicants Collate the questions into three sets of test papers Scrutinize the test papers for errors 14 H 7 I 7 Get the test papers printed and procure the sealed test papers Despatch the test papers to the test centres Prepare the list of successful applicants J 21 K 7 L 14 M Despatch admission cards to eligible applicants for examination Conduct the iesi 10 4
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Based on the given set of activities answer the following:
1. Develop a precedence for each of the activity based on the information provided in the case.
2. Draw a network diagram and also calculate the forward and the backward pass for each of the activities.
3. Identify the paths as well as the critical path for the given project and also determine the slack time for each activity.
![Activity Activity Description
Time (Days)
Prepare preliminary set of questions for the verbal section
Prepare preliminary set of questions for the quantitative section
A
15
B
20
Prepare preliminary set of questions for the data analysis section
20
Search for printers who could print the test papers
21
E
Choose the test centres
30
F
Print the application forms
14
Advertise the programme, sell application forms and receive
filled forms from applicants
G
14
Collate the questions into three sets of test papers
Scrutinize the test papers for errors
H
7
I
7
Get the test papers printed and procure the sealed test papers
Despatch the test papers to the test centres
J
21
K
7
L
Prepare the list of successíul applicants
14
Despatch admission cards to eligible applicants for examination
10
N
Conduct the iesi
4](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff4438cce-6973-46ff-a321-586214ed3c2a%2F48ea0575-7745-4a83-af8c-9b8c18773f5d%2Fipcx95p_processed.png&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 4 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)