Activity A started as planned- took 2 more days. Activity B started on day 5, was completed in the original duration. Activity E began as soon as its predecessor was completed, and has a remaining duration of 1 day. Activity C started immediately after Activity A and is 67% completed. No other activities have started. A new activity L (5 days) follows Activity F and Prcedes activity K. The duration of the other activities remains as planned. No other information is available.
Activity A started as planned- took 2 more days. Activity B started on day 5, was completed in the original duration. Activity E began as soon as its predecessor was completed, and has a remaining duration of 1 day. Activity C started immediately after Activity A and is 67% completed. No other activities have started. A new activity L (5 days) follows Activity F and Prcedes activity K. The duration of the other activities remains as planned. No other information is available.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
1
![The total project duration based on the original schedule?
O 24
O 23
O 22
O 21
The total project duration after updating the schedule?
O 29
30
О 32
31
What is the Late Start (LS) date of Activity L after updating the schedule?
O 25
O 24
O 27
O 22
What is the early start (ES) date of Activity 'F' after updating the schedule
O 16
О 10
О 12
O 14](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fabfc49ae-7f03-4e24-98e8-82a760089c22%2F84087645-d0ee-47e9-887d-0c84c3a404e5%2Fpqq920m_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The total project duration based on the original schedule?
O 24
O 23
O 22
O 21
The total project duration after updating the schedule?
O 29
30
О 32
31
What is the Late Start (LS) date of Activity L after updating the schedule?
O 25
O 24
O 27
O 22
What is the early start (ES) date of Activity 'F' after updating the schedule
O 16
О 10
О 12
O 14
![Acticity
ES
Dur
EF
LS FF TF LF
B
S5 5
E
G
K
10
FF 4
4
The planned network schedule for a project is shown below.
On data date= 14, the following schedule information was collected. (The update day is the same as
working day)
• Activity A started as planned- took 2 more days.
• Activity B started on day 5, was completed in the original duration.
• Activity E began as soon as its predecessor was completed, and has a remaining duration of 1
day.
• Activity C started immediately after Activity A and is 67% completed.
• No oth
activities have started.
• A new activity L (5 days) follows Activity F and Prcedes activity K.
• The duration of the other activities remains as planned.
• No other information is available.
Which are the critical activities based on the original schedule?](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fabfc49ae-7f03-4e24-98e8-82a760089c22%2F84087645-d0ee-47e9-887d-0c84c3a404e5%2F0ezc0re_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Acticity
ES
Dur
EF
LS FF TF LF
B
S5 5
E
G
K
10
FF 4
4
The planned network schedule for a project is shown below.
On data date= 14, the following schedule information was collected. (The update day is the same as
working day)
• Activity A started as planned- took 2 more days.
• Activity B started on day 5, was completed in the original duration.
• Activity E began as soon as its predecessor was completed, and has a remaining duration of 1
day.
• Activity C started immediately after Activity A and is 67% completed.
• No oth
activities have started.
• A new activity L (5 days) follows Activity F and Prcedes activity K.
• The duration of the other activities remains as planned.
• No other information is available.
Which are the critical activities based on the original schedule?
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 5 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning