Activity A started as planned- took 2 more days. Activity B started on day 5, was completed in the original duration. Activity E began as soon as its predecessor was completed, and has a remaining duration of 1 day. Activity C started immediately after Activity A and is 67% completed. No other activities have started. A new activity L (5 days) follows Activity F and Prcedes activity K. The duration of the other activities remains as planned. No other information is available.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

1

The total project duration based on the original schedule?
O 24
O 23
O 22
O 21
The total project duration after updating the schedule?
O 29
30
О 32
31
What is the Late Start (LS) date of Activity L after updating the schedule?
O 25
O 24
O 27
O 22
What is the early start (ES) date of Activity 'F' after updating the schedule
O 16
О 10
О 12
O 14
Transcribed Image Text:The total project duration based on the original schedule? O 24 O 23 O 22 O 21 The total project duration after updating the schedule? O 29 30 О 32 31 What is the Late Start (LS) date of Activity L after updating the schedule? O 25 O 24 O 27 O 22 What is the early start (ES) date of Activity 'F' after updating the schedule O 16 О 10 О 12 O 14
Acticity
ES
Dur
EF
LS FF TF LF
B
S5 5
E
G
K
10
FF 4
4
The planned network schedule for a project is shown below.
On data date= 14, the following schedule information was collected. (The update day is the same as
working day)
• Activity A started as planned- took 2 more days.
• Activity B started on day 5, was completed in the original duration.
• Activity E began as soon as its predecessor was completed, and has a remaining duration of 1
day.
• Activity C started immediately after Activity A and is 67% completed.
• No oth
activities have started.
• A new activity L (5 days) follows Activity F and Prcedes activity K.
• The duration of the other activities remains as planned.
• No other information is available.
Which are the critical activities based on the original schedule?
Transcribed Image Text:Acticity ES Dur EF LS FF TF LF B S5 5 E G K 10 FF 4 4 The planned network schedule for a project is shown below. On data date= 14, the following schedule information was collected. (The update day is the same as working day) • Activity A started as planned- took 2 more days. • Activity B started on day 5, was completed in the original duration. • Activity E began as soon as its predecessor was completed, and has a remaining duration of 1 day. • Activity C started immediately after Activity A and is 67% completed. • No oth activities have started. • A new activity L (5 days) follows Activity F and Prcedes activity K. • The duration of the other activities remains as planned. • No other information is available. Which are the critical activities based on the original schedule?
Expert Solution
steps

Step by step

Solved in 5 steps with 5 images

Blurred answer
Knowledge Booster
Sectioning basics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning