Activity a b с e Predecessor a с b&c Duration (weeks) 2 3 3 4 5 Budget $ 300 200 250 650 420 Actual Cost $ 400 180 315 300 280 % Complete 100 100 100 50 20
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC, and EAC for the project.
Step by step
Solved in 4 steps