Activity 4A: I conduct performance ratings for two employees of the same nature of work using the Westinghouse Rating System. The observed time for an operator to finish a task which is tightening of screws for 2 minutes. His ratings were noted, as follows: Good skill, C1 + 0.06 Excellent Efforts, B1 + 0.08 Average condition, C + 0.02 Good consistency, C + 0.01 Total Westinghouse Rating + 0.17 The normal time for that operation would be = 2.0 x 1.17 = 2.34 min. To find the standard time at 20% allowance, = 2.34 x 100 = 2.92 min. (100 – 20) Explain. Be able to describe your basis, or give comments, on how you came up with their total rating. Set the standard time at 20% allowance.
Activity 4A:
I conduct performance ratings for two employees of the same nature of work using the Westinghouse Rating System.
The observed time for an operator to finish a task which is tightening of screws for 2 minutes. His ratings were noted, as follows:
Good skill, C1 + 0.06
Excellent Efforts, B1 + 0.08
Average condition, C + 0.02
Good consistency, C + 0.01
Total Westinghouse Rating + 0.17
The normal time for that operation would be = 2.0 x 1.17 = 2.34 min.
To find the standard time at 20% allowance,
= 2.34 x 100 = 2.92 min.
(100 – 20)
Explain.
Be able to describe your basis, or give comments, on how you came up with their total rating. Set the standard time at 20% allowance.