a. Find the critical path. OA-C-D-F-G A-B-D-F-G A-C-D-E-G A-B-D-E-G The following table shows the normal times and the crash times, along with the associated costs for each activi CRASH COST $ 8,000 7,000 10, 200 ACTIVITY NORMAL TIME CRASH TIME NORMAL COST A B C D E F G 7 3 4 5 2 4 5 6 2 3 4 2 4 $7,000 5,000 9,000 3,000 2,000 4,000 5,000 4,500 3,000 7,000 8,000 b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened? O A, F, D (or E)
a. Find the critical path. OA-C-D-F-G A-B-D-F-G A-C-D-E-G A-B-D-E-G The following table shows the normal times and the crash times, along with the associated costs for each activi CRASH COST $ 8,000 7,000 10, 200 ACTIVITY NORMAL TIME CRASH TIME NORMAL COST A B C D E F G 7 3 4 5 2 4 5 6 2 3 4 2 4 $7,000 5,000 9,000 3,000 2,000 4,000 5,000 4,500 3,000 7,000 8,000 b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened? O A, F, D (or E)
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Question 100
![Here is a network with the activity times shown in days:
A(7)
a. Find the critical path.
A-C-D-F-G
A-B-D-F-G
A-C-D-E-G
A-B-D-E-G
B(3)
7
3
4
(C(4)
5
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST
A
B
с
D
E
2
4
5
The following table shows the normal times and the crash times, along with the associated costs for each activity.
6
2
(D(5)
3
4
$7,000
5,000
9,000
(F(4)
3,000
2,000
4,000
5,000
(E(2),
G(5)
CRASH COST
$ 8,000
7,000
10, 200
4,500
3,000
7,000
8,000
b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?
OA, F, D (or E)](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdd26d85a-e013-4a48-a762-d5bd9e4b812c%2Faa3e5887-4c9f-4902-8bf1-817d02e0743e%2Ftc2mip8_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Here is a network with the activity times shown in days:
A(7)
a. Find the critical path.
A-C-D-F-G
A-B-D-F-G
A-C-D-E-G
A-B-D-E-G
B(3)
7
3
4
(C(4)
5
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST
A
B
с
D
E
2
4
5
The following table shows the normal times and the crash times, along with the associated costs for each activity.
6
2
(D(5)
3
4
$7,000
5,000
9,000
(F(4)
3,000
2,000
4,000
5,000
(E(2),
G(5)
CRASH COST
$ 8,000
7,000
10, 200
4,500
3,000
7,000
8,000
b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?
OA, F, D (or E)
![a. Find the critical path.
OA-C-D-F-G
OA-B-D-F-G
A-C-D-E-G
O A-B-D-E-G
The following table shows the normal times and the crash times, along with the associated costs for each activity.
NORMAL COST
$7,000
5,000
9,000
3,000
ACTIVITY
A
B
C
D
E
F
G
NORMAL TIME CRASH TIME
7
6
3
2
4
3
5
2
4
5
4
1
2
4
b-2. Find the resulting cost to crash.
Resulting cost to crash
2,000
4,000
5,000
CRASH COST
$ 8,000
7,000
10, 200
b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?
OA, F, D (or E)
OC, F (or E), D (or E)
OA, C, D (or F), F (or D)
OE, A
4,500
3,000
7,000
8,000](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdd26d85a-e013-4a48-a762-d5bd9e4b812c%2Faa3e5887-4c9f-4902-8bf1-817d02e0743e%2Fuyopsfd_processed.jpeg&w=3840&q=75)
Transcribed Image Text:a. Find the critical path.
OA-C-D-F-G
OA-B-D-F-G
A-C-D-E-G
O A-B-D-E-G
The following table shows the normal times and the crash times, along with the associated costs for each activity.
NORMAL COST
$7,000
5,000
9,000
3,000
ACTIVITY
A
B
C
D
E
F
G
NORMAL TIME CRASH TIME
7
6
3
2
4
3
5
2
4
5
4
1
2
4
b-2. Find the resulting cost to crash.
Resulting cost to crash
2,000
4,000
5,000
CRASH COST
$ 8,000
7,000
10, 200
b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?
OA, F, D (or E)
OC, F (or E), D (or E)
OA, C, D (or F), F (or D)
OE, A
4,500
3,000
7,000
8,000
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
Step 1 Introduction:-
A network diagram shows the sequence of the task that is done to complete a project. It usually shows the link of each task with the duration taken by each activity with respect to the completion of the project. Each task is shown with the nodes that are connected with each other with the help of arrows. There are 2 types of network diagrams:- CPM and PERT.
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 7 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.