a. Draw the project network. b. Identify the critical path(s). C. Find the total project completion time and total project cost using the normal times.
a. Draw the project network. b. Identify the critical path(s). C. Find the total project completion time and total project cost using the normal times.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Give handwritten solution.

Transcribed Image Text:2. As a result of a bank merger, two financial processing software systems must be integrated.
The "systems integration team" has come up with the following tasks, their predecessor
relations, and estimates for task durations and crash costs:
Normal time
A
B
C
D
E
F
G
H
Activity
e.
f.
Immediate
Predecessor(s)
-
A
A
B,C
C
D
D.E
F.G
15
9
10.
3
9
10
10
7
Crash time
10
8
6
3
7
8
7
Normal cost
($)
900
800
2500
4000
2000
1500
1000
2000
Crash cost
($)
3900
1100
3500
4000
2800
2400
1200
a. Draw the project network.
b. Identify the critical path(s).
C. Find the total project completion time and total project cost using the normal times.
d. Find the total project completion time and total project cost if the project must be completed two
weeks early.
Find the shortest time in which the project can be completed.
Find the crashing schedule that minimizes total project cost.
2000
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.