a. Draw the network diagram in AOA and AON. b. Show the critical Path for the project?, And determine project completion time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question
Given the following table which represents the activities included in one of
the construction project. (Times are given in weeks):
Activity
A
B
C
D
E
F
G
H
I
J
Preceding
Activity
-
A
B
A
B, D
C, E
F
C
G, H
I
Normal time
(weeks)
10
8
10
7
11
3
6
3
9
5
Crash time
(weeks)
8
6
8
6
9
3
5
1
6
3
Normal Crashed
Cost Cost
30
40
120
150
100
160
40
50
50 75
60
100
140
30
40
150 270
180 190
-
a. Draw the network diagram in AOA and AON.
b. Show the critical Path for the project?, And determine project
completion time?
Transcribed Image Text:Given the following table which represents the activities included in one of the construction project. (Times are given in weeks): Activity A B C D E F G H I J Preceding Activity - A B A B, D C, E F C G, H I Normal time (weeks) 10 8 10 7 11 3 6 3 9 5 Crash time (weeks) 8 6 8 6 9 3 5 1 6 3 Normal Crashed Cost Cost 30 40 120 150 100 160 40 50 50 75 60 100 140 30 40 150 270 180 190 - a. Draw the network diagram in AOA and AON. b. Show the critical Path for the project?, And determine project completion time?
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.