(a) What is the Predetermined overhead rate? (Round your answer to 2 decimal places.) Predetermined overhead rate per machine-hour (b) By how much is the manufacturing overhead underapplied or overapplied? manufacturing overhead

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

Info in images

2. Change all of the numbers in the data area of your worksheet so that it looks like this:
A
В
C
1
Chapter 3: Applying Excel
Data
4
Allocation base
Machine-hours
Estimated manufacturing overhead cost
$
713,400
6.
Estimated total amount of the allocation base
87,000 machine-hours
7
Actual manufacturing overhead cost
695,900
8.
Actual total amount of the allocation base
86,000 machine-hours
If your formulas are correct, you should get the correct answers to the following questions.
(a) What is the Predetermined overhead rate? (Round your answer to 2 decimal places.)
Predetermined overhead rate
per machine-hour
(b) By how much is the manufacturing overhead underapplied or overapplied?
manufacturing overhead
24
3.
Transcribed Image Text:2. Change all of the numbers in the data area of your worksheet so that it looks like this: A В C 1 Chapter 3: Applying Excel Data 4 Allocation base Machine-hours Estimated manufacturing overhead cost $ 713,400 6. Estimated total amount of the allocation base 87,000 machine-hours 7 Actual manufacturing overhead cost 695,900 8. Actual total amount of the allocation base 86,000 machine-hours If your formulas are correct, you should get the correct answers to the following questions. (a) What is the Predetermined overhead rate? (Round your answer to 2 decimal places.) Predetermined overhead rate per machine-hour (b) By how much is the manufacturing overhead underapplied or overapplied? manufacturing overhead 24 3.
B23
fx
=B18-B22
A
В
C
1 Chapter 3: Applying Excel
3 Data
4 Allocation base
Machine-hours
$300,000
75,000 machine-hours
$290,000
68,000 machine-hours
5 Estimated manufacturing overhead cost
6 Estimated total amount of the allocation base
7 Actual manufacturing overhead cost
8 Actual total amount of the allocation base
9.
10 Enter a formula into each of the cells marked with a ? below
11
12 Computation of the predetermined overhead rate
13 Estimated manufacturing overhead cost
14 Estimated total amount of the allocation base
15 Predetermined overhead rate
$300,000
75,000 machine-hours
$4.00 per machine-hour
16
17 Computation of underapplied or overapplied manufacturing overhead
18 Actual manufacturing overhead cost
19 Manufacturing overhead cost applied to Work in Process during the year:
$ 290,000
$4.00 per machine-hour
68,000 machine-hours
$ 272,000
$
20
Predetermined overhead rate
21
Actual total amount of the allocation base
Manufacturing overhead applied
23 |Underapplied (overapplied) manufacturing overhead
22
18,000
24
25
26
27
28
20
Transcribed Image Text:B23 fx =B18-B22 A В C 1 Chapter 3: Applying Excel 3 Data 4 Allocation base Machine-hours $300,000 75,000 machine-hours $290,000 68,000 machine-hours 5 Estimated manufacturing overhead cost 6 Estimated total amount of the allocation base 7 Actual manufacturing overhead cost 8 Actual total amount of the allocation base 9. 10 Enter a formula into each of the cells marked with a ? below 11 12 Computation of the predetermined overhead rate 13 Estimated manufacturing overhead cost 14 Estimated total amount of the allocation base 15 Predetermined overhead rate $300,000 75,000 machine-hours $4.00 per machine-hour 16 17 Computation of underapplied or overapplied manufacturing overhead 18 Actual manufacturing overhead cost 19 Manufacturing overhead cost applied to Work in Process during the year: $ 290,000 $4.00 per machine-hour 68,000 machine-hours $ 272,000 $ 20 Predetermined overhead rate 21 Actual total amount of the allocation base Manufacturing overhead applied 23 |Underapplied (overapplied) manufacturing overhead 22 18,000 24 25 26 27 28 20
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Rental Agreement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education