A wastewater treatment plant must disinfect its effluent before discharging the wastewater to a nearby stream. The wastewater contain 5.5 x 1^5faecal coliform coliform – forming units (CFU) per liter. The maximum permissible faecal coliform concentration that may be discharged is 3000 faecalcoliform CFU/L. It is proposed that a pipe carrying the wastewater be used for disinfection process. Determine the length of pipe required if the linear velocity of the wastewater pipe is 0.85 m/s. Assume that the pipe behaves as a steady-state plug flow system and that the reaction rate constant for destruction of the feacal coliform is 0.22 per min.
A wastewater treatment plant must disinfect its effluent before discharging the wastewater to a nearby stream. The wastewater contain 5.5 x 1^5faecal coliform coliform – forming units (CFU) per liter. The maximum permissible faecal coliform concentration that may be discharged is 3000 faecalcoliform CFU/L. It is proposed that a pipe carrying the wastewater be used for disinfection process. Determine the length of pipe required if the linear velocity of the wastewater pipe is 0.85 m/s. Assume that the pipe behaves as a steady-state plug flow system and that the reaction rate constant for destruction of the feacal coliform is 0.22 per min.
![](/static/compass_v2/shared-icons/check-mark.png)
Given data:
Initial concentration of California colony (Co) = 5.5 x 105 CFU/L.
Maximum California concentration discharged © = 3000 CFU/L
Velocity (V) = 0.85 m/s
Reaction rate constant (k)= 0.22 min-1
Consider reaction rate (A steady state plug flow first order system) equation for PFR:
Step by step
Solved in 3 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)