A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table. Activity A. find client B. write prospectus C. obtain approval from client and professor Time Immediate Predecessor 5 3 A 5 B D. complete programming 13 C E. do industry background research 10 F. write final paper G. write oral report 6 5 D, E D, E Both written and oral reports are required. Draw the project network. Can they complete the project in the 41 class days remaining until the end of the semester? ---Select--- ✓ , they can complete it in time since the project is expected to be completed in ' days.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

am. 178.

A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
Activity
A. find client
B. write prospectus
C. obtain approval from client and professor
Time Immediate Predecessor
5
3
A
5
B
D. complete programming
13
C
E. do industry background research
10
F. write final paper
G. write oral report
6
5
D, E
D, E
Both written and oral reports are required. Draw the project network. Can they complete the project in the 41 class days remaining until the end of the semester?
---Select--- ✓ , they can complete it in time since the project is expected to be completed in
'
days.
Transcribed Image Text:A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table. Activity A. find client B. write prospectus C. obtain approval from client and professor Time Immediate Predecessor 5 3 A 5 B D. complete programming 13 C E. do industry background research 10 F. write final paper G. write oral report 6 5 D, E D, E Both written and oral reports are required. Draw the project network. Can they complete the project in the 41 class days remaining until the end of the semester? ---Select--- ✓ , they can complete it in time since the project is expected to be completed in ' days.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.