A project that provides annual cash flows of $17,800 for eight years costs $84,000 today. What is the NPV for the project if the required return is 7 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places, e.g., 32.16.) At a required return of 7 percent, should the firm accept this project? multiple choice 1 Accept Reject What is the NPV for the project if the required return is 19 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 19 percent, should the firm accept this project? multiple choice 2 Accept Reject At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
A project that provides annual cash flows of $17,800 for eight years costs $84,000 today. |
What is the NPV for the project if the required return is 7 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places, e.g., 32.16.) |
At a required return of 7 percent, should the firm accept this project? |
multiple choice 1
|
What is the NPV for the project if the required return is 19 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
At a required return of 19 percent, should the firm accept this project? |
multiple choice 2
|
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) |