A project has estimated optimistic (a), most likely (m) and pessimistic (b) times for activity D as 7, 8 and 14 days, respectively. What is the mean AND variance for activity D, respectively (to 1 decimal place): Select one: a. 8.8 and 1.2 b. 8.5 and 0.7 C. 8.8 and 0.7 d. 9.7 and 1.4

A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
icon
Related questions
Question
A project has estimated optimistic (a), most likely (m) and pessimistic (b) times for activity D
as 7, 8 and 14 days, respectively. What is the mean AND variance for activity D, respectively
(to 1 decimal place):
Select one:
a. 8.8 and 1.2
b. 8.5 and 0.7
O c. 8.8 and 0.7
d. 9.7 and 1.4
Transcribed Image Text:A project has estimated optimistic (a), most likely (m) and pessimistic (b) times for activity D as 7, 8 and 14 days, respectively. What is the mean AND variance for activity D, respectively (to 1 decimal place): Select one: a. 8.8 and 1.2 b. 8.5 and 0.7 O c. 8.8 and 0.7 d. 9.7 and 1.4
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
A First Course in Probability (10th Edition)
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability
A First Course in Probability
Probability
ISBN:
9780321794772
Author:
Sheldon Ross
Publisher:
PEARSON