A pipeline engineer working in Kuwait for the oil giant BP wants to perform a present worth analysis on alternative pipeline routings-the first predominately by land and the second primarily undersea. The undersea route is more expensive initially due to extra corrosion protection and installation costs, but cheaper security and maintenance reduces annual costs. . Perform the annual worth analysis for the engineer at 12% per year as basis of choosing which route is to be selected. Land Undersea Installation cost P 315,000,000 P 450,000,000 Pumping, operating, security per year P 18,000,000 P 4,200,000 Replacement appurtenances in year 25 of valves and P 40,000,000 P 85,000,000 Life, years 50 50

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
A pipeline engineer working in Kuwait for the oil giant BP wants to perform a present worth analysis on alternative pipeline routings-the first
predominately by land and the second primarily undersea. The undersea route is more expensive initially due to extra corrosion protection and
installation costs, but cheaper security and maintenance reduces annual costs. Perform the annual worth analysis for the engineer at 12% per
year as basis of choosing which route is to be selected.
Land
Undersea
Installation cost
P 315,000,000
P 450,000,000
Pumping, operating, security per year
P 18,000,000
P 4,200,000
Replacement
of
valves
and
P 40,000,000
P 85,000,000
appurtenances in year 25
Life, years
50
50
Transcribed Image Text:A pipeline engineer working in Kuwait for the oil giant BP wants to perform a present worth analysis on alternative pipeline routings-the first predominately by land and the second primarily undersea. The undersea route is more expensive initially due to extra corrosion protection and installation costs, but cheaper security and maintenance reduces annual costs. Perform the annual worth analysis for the engineer at 12% per year as basis of choosing which route is to be selected. Land Undersea Installation cost P 315,000,000 P 450,000,000 Pumping, operating, security per year P 18,000,000 P 4,200,000 Replacement of valves and P 40,000,000 P 85,000,000 appurtenances in year 25 Life, years 50 50
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Break-even Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education