A negative value for slack indicates: the problem is feasible O the problem is infeasible there may be additional solutions
Q: John is a Training Specialist for a retail operation in Omaha, NE. His normal hours are 8am – 5pm…
A: Labor law plays a critical role in shaping the relationship between employers and employees,…
Q: Mario, a security guard, has drawn a shift of 6:00 p.m. to 2:00 a.m. from Teusday to Sunday getting…
A: Shift timings: 6:00 p.m. to 2:00 a.mShift days: Tuesday, Wednesday, Thursday, Friday, Saturday,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the total time spent to manufacture a single unit of item.
Q: Mustafiz is bowling beautiful cutters against the Aussies. He has bowled on the first over and also…
A: Given The first over is 25 and the last over is 511. The last over would be up to ball no. 4
Q: E What will be the idle time for the LAST Workstation?
A: Line balancing is the process of arranging the activities to different workstations based on duck…
Q: Pascal James is an avid Toronto sports fan and is invited by his best friend to a Toronto Raptors…
A: The objective of the question is to provide legal advice to Pascal, who has suffered serious…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the actual total time incurred in manufacturing a product by the team members in an…
Q: What will be the idle time for the
A: Idle time for each workstation indicating the balance time after allocating all possible activities…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output = 60 units Available time = 8 hrs or 8*60 = 480 min
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data: Production line = 8 hours per day Demand = 90 units per day Task Task time Immediate…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand = 100 units Time available = 8×60= 480 minutes
Q: i can I get help on this please? I am stuck!! Question: lumber and plywood. In a given week, the…
A: LumberPlywoodProfit2538Quantity Produced 11400Quantity Required 10100Quantity Required 01150
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: FCFS stands for First-Come, First-Served. It is a type of scheduling algorithm.In this type of…
Q: Four automobiles have entered Bubba’s Repair Shop for various types of work, ranging from a…
A: Consider the provided question, According to the given question, let assume for work as J1, J2, J3,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: SPT sequence: Sequence -Select- -Select- -Select- -Select- Processing Time Due Date Average How…
A: Sequencing involves deciding the order in which tasks or jobs are performed in a production or…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F…
Q: A manufacturer is designing a product layout fora new produc hours per day in order to meet…
A: Demand= 70 units Time available= 8*70= 560 minutes Cycle time= time available/ demand= 560/60= 9.3…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Production time= 8*60= 480 minutes Demand= 100 units Cycle time= production time/ demand= 480/100=…
Q: Brown's Machining has three jobs with the routings and processing times (in minutes) as indicated on…
A: Processing time states the amount of time that is taken by machinery or a workstation to complete a…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: Using the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three…
A: Given-
Q: The emergency room of the Time Between Arrivals (min.) community hospital in Farmburg has one…
A: The probability distribution provides the likelihood of occurrence of different values taken by some…
Q: One possible solution method for the machine-to job assignment problem is the following heuristic…
A: Yes, this heuristic provides the most efficient method of task assignment because projects done on…
Q: What will be the idle time
A: Line balancing the process of allocating activities based on the cycle time and available tie…
Q: 3) Alice works as an Order Processor at a local retail store. She is an hourly employee and her…
A: Alice's compensable time would begin at 8:00 AM. The FLSA defines compensable time as any time that…
Q: 1) A worker travels between her home and work. She has multiple routes that can be taken. Her first…
A: The most common way of picking a way for traffic inside an organization, or across or across a large…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: PROBLEM 10 The Graphic Palette is a firm in Charleston, South Carolina, that does graphic artwork…
A: Consider the machine routing as a network of the machines. Objective function: Min Cost = ∑Cij×Xij…
Q: Sequence 1 2 3 4 Job A B C D The average tardiness (job lateness) for the sequence developed using…
A: Let me state the given data, Today's day is 205,
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data is Demand = 80units/day Working hours = 8
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Daily Working hour= 8 hours Daily Demand = 90 units Sum of total task time =…
Q: Develope serpate schedules by using the FCF and EDS rules. Using FCF, the order is Using EDS, the…
A: Here, I will use two rules FCFS and EDD rules, for each rule I will determine the order, the average…
Q: According to the following assignment problem, what should be the constraint associated with job B?…
A: Job Assignment-
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The efficiency can be determined as follows: Efficiency = Sum of total task timesNumber of…
Q: The current date is day 275 and the following jobs are waiting to be processed at the same…
A: Given-
Linear programming is a mathematical model for finding the maximum or minimum of a linear function of many variables. It can be used to solve problems in which we are trying to maximize or minimize some objective function, subject to some constraints.
Step by step
Solved in 2 steps
- A convenience store manager earns a base salary plus a small bonus of $190 for each of ten different possible monthly milestones he meets. If the manager meets a milestone, the full bonus is paid. However, if the manager falls even one penny short, none of that bonus is paid. Suppose each of the ten milestones requires 40 hours of effort to meet, and that the manager has 160 hours of effort to allocate to work each month. Question: In order to maximize the total monthly bonus, the manager should allocate___hours toward meeting each of ___ milestones and ___hours toward meeting each of the remaining___ sales milestones. There are 4 blanks to fill for this questionSmith Inc. is a retail mail order firm that currently uses a centralized collection system that requires all checks to be sent to its flotation headquarters. An average of 6 days is required for mailed checks to be received, 3 days for Smith Inc. to process them, and 2 days for the checks to clear through its bank. A proposed lockbox system would decrease the mailing and processing time to 2 days and the check clearing time for 1 day. Smith Inc. has an average daily collection of P250,000. If Smith Inc. adopts this proposed lockbox system, its average cash balance will increase by. A. 1.2M B. 450k C. 750k D. 2MA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? Select one: Oa. 4.5 Ob. 0.9 Oc. None is the correct answer O d. 6.0 Oe. 4.4 Next pa nd Windows
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 110 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? O a. 1 Ob. 2 c. 6. O d. None is the correct answer O e. 4 82°F Mostly cle acerIn an evaluation of labor assignment rules when workers are not perfectly interchangeable, Paul. M. Bobrowski and Paul Sungchil Park created a dynamic job shop with 9 work centers and 9 workers, both numbered 1–9. The efficiency of each worker is specified in the following labor efficiency matrix, which represents the degree of worker cross-training.† Work Centers 1.00 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 1.00 0.95 0.95 0.95 0.95 0.95 0.85 0.85 0.85 0.85 1.00 W o r k e r s (a) For what work center(s) is worker 2 least efficient? (Enter your answers as a comma-separated list.) (b) For what…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the LAST workstation are O a. All tasks O b. Gonly…
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C D E F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed, Starting tasks needs the task to be completed. Also starting task D, needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 28.2.1,0.9, 10, 1.2.1.8 are 4.7 minutes respectively. How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5 please I neef answer along with the formula don't put it on excelA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? a. 31.34 O b. 81.82 O c. None is the correct…One possible solution method for the machine-tojob assignment problem is the following heuristic procedure. Assign the machine to job 1 that completes job 1 quickest. Then assign the machine to job 2 that, among all machines that still have some capacity, completes job 2 quickest. Keep going until a machine has been assigned to all jobs. Does this heuristic-procedure yield the optimal solution for this problem? If it does, see whether you can change the job times so that the heuristic does not yield the optimal-solution.
- The Safe Zone Restaurant, a 24-hour restaurant, faces changing requirements from hour to hour. More workers are needed for peak hours, and fewer are needed in between. The following table shows the worker requirement for the first 12 hours in the restaurant: Table 8. Staff Requirement at the Safe Zone Restaurant Time Period 10 11 12 1 PM|2 PM|3 PM|4 PM|5 PM|6 PM 7 PM|8 PM|9 PM АM | АM | РМ Requirement 7 Assigned On Duty Overstaffed 9 10 10 8 6 6. 8 8 12 12 8 a) You are required to apply the first-hour principle to staff each hour with the required number of cafeteria staff, showing how many staff are on duty each given hour, the number of staff you have assigned to work each hour and any overstaffing for each hour. i. Schedule the staff to work in 8-hour shifts. ii. Schedule the staff to work in 4-hour shifts. b) Indicate with at least one reason, which schedule would be more optimal from an Operations Scheduling perspective?2A-ATTACHEDNote:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.