A firm has established a distribution network for the supply of a raw material critical to its manufacturing. Currently there are two origins for this material, which must be shipped to three manufacturing plants. The current network has the following characteristics: COSTS PLANT 1 PLANT 2 PLANT 3 SUPPLY Raw Material source 1 $6 $8 $9 400 Raw Material source 2 $4 $7 $3 600 Demand 500 500 500 Supply < Demand The firm has identified two potential sites for a third raw material source; these are identified as Candidate A and Candidate B. From A, the costs to ship would be $9 to Plant 1, $10 to Plant 2, and $12 to Plant 3. From B, these costs would be $11, $14, and $8. The new source, wherever it is located, will have a capacity of 500 units. Solve with the transportation method. Which site should be selected?
A firm has established a distribution network for the supply of a raw material critical to its
manufacturing. Currently there are two origins for this material, which must be shipped to three
manufacturing plants. The current network has the following characteristics:
COSTS | PLANT 1 | PLANT 2 | PLANT 3 | SUPPLY |
Raw Material source 1 | $6 | $8 | $9 | 400 |
Raw Material source 2 | $4 | $7 | $3 | 600 |
Demand | 500 | 500 | 500 | Supply < Demand |
The firm has identified two potential sites for a third raw material source; these are identified as
Candidate A and Candidate B. From A, the costs to ship would be $9 to Plant 1, $10 to Plant 2,
and $12 to Plant 3. From B, these costs would be $11, $14, and $8. The new source, wherever it
is located, will have a capacity of 500 units. Solve with the transportation method. Which site
should be selected?