A firm has a capital budget of $30,000 and is considering three possible independent projects. Project A has a present outlay of $12,000 and yields $4, 281 per annum for 5 years. Project B has a present outlay of $10,000 and yields $4,184 per annum for 5 years. Project C has a present outlay of $17,000 and yields $5,802 per annum for 10 years. Funds which are not allocated to one of the projects can be placed in a bank deposit where they will earn 15%. (a) Identify six combinations of project investments and a bank deposit which exhaust the budget. (b) Which of the above combinations should the firm choose: (i) When the reinvestment rate is 15%? (ii) When the reinvestment rate is 20%?
5) A firm has a capital budget of $30,000 and is considering three possible independent projects. Project A has a present outlay of $12,000 and yields $4, 281 per annum for 5 years. Project B has a present outlay of $10,000 and yields $4,184 per annum for 5 years. Project C has a present outlay of $17,000 and yields $5,802 per annum for 10 years. Funds which are not allocated to one of the projects can be placed in a bank deposit where they will earn 15%.
(a) Identify six combinations of project investments and a bank deposit which exhaust the budget.
(b) Which of the above combinations should the firm choose:
(i) When the reinvestment rate is 15%?
(ii) When the reinvestment rate is 20%?
Explain your answer and show your calculations (spreadsheet printout is acceptable as long as entries are clearly labeled).
Trending now
This is a popular solution!
Step by step
Solved in 2 steps