A custom guitar shop sells two types of guitan electric and acoustic. The creation process of each guitar is broken into three parts: building the base guitar, applying the finish/paine, and adding accessories. The time requirements (in days) and the total days available for each phase of the creation process are listed below Base Guitar Creation Applying the Finisl/Paint Adding Accessories 3. Electric Acoustic Total Days 360 240 300 If they proft $10o from each electric guitar and $900 from each acoustic guitar, how many of each uitar type should be made to maximize the shop's profie What is the shop's maximum proft? Determine if the shop has any lehover time for each task, entering if no time is leftover. The masimum profit is s when electric guitan and acoustic guitarn are made. There are days lefover for building base gairans days leftover for applying finish/paint, and days leftover for adding accessories,

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
Question
7
A custom guitar shop sells two types of guitars: electric and acoustic. The creation process of each guitar is broken into three parts: building the base guitar, applying the
finish/paint, and adding accessories. The time requirements (in days) and the total days available for each phase of the creation process are listed below.
Base Guitar Creation Applying the Finish/Paint Adding Accessories
Electric
2.
Acoustic
Total Days
360
240
300
If they proft $105o from each electric guitar and $900 from each acoustic guitar, how many of each guitar type should be made to maximize the shop's profie What is the
shop's maximum proft? Determine if the shop has any lefiover time for each task, entering 0 if no time is lefrover.
The maximum proht is $
when
electric guitan and
acoustic guitars are made.
There are
days lefrover for building base guitan,
days leftover for applying finith/paint, and
days leftover for adding accesories,
Transcribed Image Text:A custom guitar shop sells two types of guitars: electric and acoustic. The creation process of each guitar is broken into three parts: building the base guitar, applying the finish/paint, and adding accessories. The time requirements (in days) and the total days available for each phase of the creation process are listed below. Base Guitar Creation Applying the Finish/Paint Adding Accessories Electric 2. Acoustic Total Days 360 240 300 If they proft $105o from each electric guitar and $900 from each acoustic guitar, how many of each guitar type should be made to maximize the shop's profie What is the shop's maximum proft? Determine if the shop has any lefiover time for each task, entering 0 if no time is lefrover. The maximum proht is $ when electric guitan and acoustic guitars are made. There are days lefrover for building base guitan, days leftover for applying finith/paint, and days leftover for adding accesories,
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 8 steps with 1 images

Blurred answer
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,