A contractor has been asked to quote for a job and has the following information available about the costs: Notes: 1. The contract requires 400,000 bricks of this standard type. The contractor has 200,000 already in stock and will need to buy 200,000. The 200,000 at P100 per 1,000 in the quote above were bought at that price earlier in the year. The current replacement cost for this type of brick is P120 per 1,000. If the bricks are not used on this project the contractor is confident that he will be able to use them later on in the year. 2. This is the purchase price of other materials that will be bought in as required. 3. The contractor intends to work 800 hours of the skilled work himself and hire the rest in on an hourly basis at P12 per hour. If the contractor does not take on this job he can either work for other contractors at P12 per hour or complete urgently required work to his own house for which he has been quoted P12,000 by another contractor. 4. The contractor has 4 unskilled laborers employed on a contract guaranteeing them 40 hours per week at P6 per hour.They are currently idle and have spare time available to complete the job. 5. This is the estimated cost of hiring scaffolding. 6. The job will take 20 weeks and the machine will not be used on any other job if this job is not taken on. 7. This represents the cost of the storage yard used by the contractor. If this is not used it can be rented out to a competitor for the 20 week period at a rent of P500 per week. 8. This is the cost of drawing up the plans for the project. These were drawn up several weeks ago. 9. A mark up of 20% is added to all jobs. Required: 1.) Explain how each item described above should be treated. 2.)  Using relevant costing principles, calculate the lowest price that the contractor could quote for the building work.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

A contractor has been asked to quote for a job and has the following information available about the costs:

Notes:
1. The contract requires 400,000 bricks of this standard type. The contractor has 200,000 already in stock and will need to buy 200,000. The 200,000 at P100 per 1,000 in the quote above were bought at that price earlier in the year. The current replacement cost for this type of brick is
P120 per 1,000. If the bricks are not used on this project the contractor is confident that he will be able to use them later on in the year.
2. This is the purchase price of other materials that will be bought in as required.
3. The contractor intends to work 800 hours of the skilled work himself and hire the rest in on an hourly basis at P12 per hour. If the contractor does not take on this job he can either work for other contractors at P12 per hour or complete urgently required work to his own house for which he has been quoted P12,000 by another contractor.

4. The contractor has 4 unskilled laborers employed on a contract guaranteeing them 40 hours
per week at P6 per hour.They are currently idle and have spare time available to complete the job.
5. This is the estimated cost of hiring scaffolding.
6. The job will take 20 weeks and the machine will not be used on any other job if this job is not taken on.
7. This represents the cost of the storage yard used by the contractor. If this is not used it
can be rented out to a competitor for the 20 week period at a rent of P500 per week.
8. This is the cost of drawing up the plans for the project. These were drawn up several weeks ago.
9. A mark up of 20% is added to all jobs.

Required:
1.) Explain how each item described above should be treated.
2.)  Using relevant costing principles, calculate the lowest price that the
contractor could quote for the building work.

Item
Detail
Direct Materials
Bricks
200,000 at P100 per thousand.
20,000
Note 1
200,000 at P120 per thousand.
24,000
Other Materials
5,000
Note 2
Direct Labor
Skilled
3,200 hrs at P12 per hour
38,400
Note 3
Unskilled
2,000 hrs at P6 per hour
12,000
Note 4
Other Costs
Scaffolding hire
3,500
Note 5
Depreciation of general purpose machinery
2,000
Note 6
General overheads
5,200 hrs at P1 per hour
5,200
Note 7
Plans
2.000
Note 8
Total Cost
112,100
Profit
22,420
Note 9
Suggested Price
134,520
Transcribed Image Text:Item Detail Direct Materials Bricks 200,000 at P100 per thousand. 20,000 Note 1 200,000 at P120 per thousand. 24,000 Other Materials 5,000 Note 2 Direct Labor Skilled 3,200 hrs at P12 per hour 38,400 Note 3 Unskilled 2,000 hrs at P6 per hour 12,000 Note 4 Other Costs Scaffolding hire 3,500 Note 5 Depreciation of general purpose machinery 2,000 Note 6 General overheads 5,200 hrs at P1 per hour 5,200 Note 7 Plans 2.000 Note 8 Total Cost 112,100 Profit 22,420 Note 9 Suggested Price 134,520
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Cost classification
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education