A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid ₱ 120.00 a day, 25 at ₱ 180.00 a day, and 5 at ₱ 250.00 a day. For each day beyond the original 100 days, the contractor has to pay ₱ 500.00 liquidated damages.
Q: HELLO! PLEASE TELL ME IF I DID THIS ONE CORRECTLY. IF NOT, PLEASE HELP ME SOLVE IT. THANK YOU!…
A: Dear Student…
Q: d, if the contractor was able to finish the building earlier than agreed, it will be rewarded an…
A: In the given situation, a construction contract was agreed upon at certain price with an cost…
Q: Jeff Heun, president of Flounder Always, agrees to construct a concrete cart path at Dakota Golf…
A: Given, Jeff Heun agrees to construct a concrete cart path. Contract Price at the time of entering =…
Q: On January 1, 2016, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: The percentage of completion method reports revenues and expenses in terms of the work completed to…
Q: Required Compute the tax payable by Mr Bo Kau Looi for the year of assessment 2021.
A: Introduction: Your tax obligation refers to the amount of money you owe to taxing authorities such…
Q: Jeff Heun, president of Flint Always, agrees to construct a concrete cart path at Dakota Golf Club.…
A: Particulars Probability Workings Amount Estimated amount Project completed on time 50% 34,000…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Answer - Given, Estimated total cost of contract for the 10 houses = P40M. In CY 20x6, total…
Q: Karl Yates needs $7000 to pay for the remodeling work on his house. A contractor agrees to do the…
A: Given the information in question Karl need $7000 Time period of 2 months Interest rate = 5.9% (it…
Q: A contractor is constructing a project for which he will be paid in one lump sum upon satisfactory…
A: Loan for the first 6 months=$700,000 , interest rate = 1.5% per month for the first 10 month Loan…
Q: Infotech Bhd enters a contract on 1 January 2019 to produce software for a customer for RM5,000,000.…
A: The question is given for preparing the journal entries in the book of Macro Tech company.…
Q: ohn got a new job through Island Recruiting Company.The job pays $55K per year, and the agency fee…
A: Salary or Job payout is the compensation paid by the employer to employee for the work completed. It…
Q: A professional photographer who specializes in wedding-related activities paid $45,000 for equipment…
A: Break-even describes the point at which the connected value of variables becomes zero, such as in…
Q: Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf…
A: Calculate the performance bonus based on other jobs as follows: The amount is reducing by $10,000…
Q: John William, president of Crane Always, agrees to construct a concrete cart path at Windsor Golf…
A: Transaction price that Crane Always should compute for this agreement : = Price + Performance bonus…
Q: (b) According to the new renumeration scheme, the starting pay of a technician is RM2029 per month…
A: Meaning of Remuneration:- It's the compensation that an employee gets. It is the base salary and the…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Construction accounting requires a special revenue recognition rules for contract in procee.in this…
Q: On April 1st, Ma Construction entered into a contract of one-month duration to build a barn for…
A: Discounts, credits, rebates, performance bonuses, penalties, sales returns, refunds, price…
Q: Jeff Heun, president of Bridgeport Always, agrees to construct a concrete cart path at Dakota Golf…
A: Part a) Statement of determination of Transaction Price Date Probability Base Pay Expected…
Q: On April 1st, Bob the Builder entered into a contract of one-month duration to build a barn for…
A: The objective of this question is to calculate the expected transaction price for Bob the Builder's…
Q: Sugar has entered into a long-term contract to build an asset for a customer, Hewer. Sugar will…
A: Long term contract indicates the contract related to the completion of the given task for the client…
Q: oseph Taylor, president of Carla Vista Always, agrees to construct a concrete cart path at Vaughn…
A: The formula used to compute the transaction price that Crane Vista Always should compute for this…
Q: A building constructor has a contract which will expire in 50 days. He has 80 men on the job and can…
A: According to the given question, we are required to find out the answers. In the present scenario,…
Q: Determine the transaction price that Pina Always should compute for this agreement. Transaction…
A: Transaction price: Transaction price is the amount of consideration that is estimated by the…
Q: Oscar’s Environmental Services Inc. has a three-year contract to remove and recycle waste weekly…
A: Revenue Recognition: Revenue recognition is a generally accepted accounting standard (GAAP) that…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Current assets refer to any form of asset that is monetary beneficial for an individual or an entity…
Q: contractor has a job which should be completed in 135 days. At present, he has 80 men on the job and…
A: Liquidated damages =(160-135) *520 =13000 80 Men completed in 160 days. To complete in 135…
Q: A contractor has 50 men of the same capacity. They can complete the work in 30 days, the working day…
A: Total cost is the amount incurred by the company on the production process and business functions of…
Q: Wildhorse Always enters into a contract with Dakota to construct the path for $233,000. In addition,…
A: Solution a: Consideration Bonus Amount Probability of Outcome Revenue Recognized Bonus if…
Q: and it has acquired and, when construction is complete, to deliver the finished houses to their…
A: As per the fundamental accounting principle a revenue should be recognised only when it is earned.…
Q: Assume that Jeff Heun has reviewed his workschedule and decided that it makes sense to complete this…
A: Step 1 Basically in contracts agreements, rewards are always adjusted with the probability factor…
Q: Infotech Bhd enters a contract on 1 January 2019 to produce software for a customer for RM7,000,000.…
A: Revenue recognition refers to the concept used in accounting on an accrual basis which defines the…
Q: An engineer failing to complete his first building contract worth P70,000 in a specified time is…
A: concept. penalty amount = contract amount * specified penalty percentage.
Q: Determine the transaction price that Marin should compute for this agreement.
A: Transaction price= Contract cost + Variable consideration Variable consideration is the sum of…
A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid ₱ 120.00 a day, 25 at ₱ 180.00 a day, and 5 at ₱ 250.00 a day. For each day beyond the original 100 days, the contractor has to pay ₱ 500.00 liquidated damages.
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
- A building constructor has a contract which will expire in 50 days. He has 80 men on the job and can finish the job in 80 days. The wage per day of 40 men is P800.00 each and that of the other 40 men is P500.00 each for 8 hours work per day. The fine or liquidated damages for delay in the work is P15,000.00 per day. How many more men should the contractor add in order to enable him to complete the work on time? Assuming that the additional men to be added will be paid P500.00 per day, will the contractor save money by employing enough men for him to complete the work on time or by not adding more men and paying the fine? How much is the savings, if any? No overtime work is permittedOn January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following information pertains to the said contract each customer is to sign. Each house costs P4,000,000 each (a total of 10 houses are to be constructed). Construction will take 2 years to complete. Payment terms are 50% by the end of the 1" year, 25% at the end of the 2nd year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6. Total cost of land - P2M; Estimated total cost of construction - P25M, (including the costs for the common areas, streets and light posts amounting to P5M); Estimated total cost of contract for the 10 houses-P40M; In CY 20x5, total…On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following information pertains to the said contract each customer is to sign. Each house costs P4,000,000 each (a total of 10 houses are to be constructed). Construction will take 2 years to complete. Payment terms are 50% by the end of the 1 year, 25% at the end of the 2nd year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6. Total cost of land-P2M; Estimated total cost of construction - P25M, (including the costs for the common areas, streets and light posts amounting to PSM); Estimated total cost of contract for the 10 houses - P40M; In CY 20x6, total…
- On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following information pertains to the said contract each customer is to sign. Each house costs P4,000,000 each (a total of 10 houses are to be constructed). Construction will take 2 years to complete. Payment terms are 50% by the end of the 1" year, 25% at the end of the 2nd year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6. Total cost of land – P2M; Estimated total cost of construction – P25M, (including the costs for the common areas, streets and light posts amounting to P5M); Estimated total cost of contract for the 10 houses - P40M; In CY 20x6, total…An engineer failing to complete his first building contract worth P70,000 in a specified time is compelled to pay a penalty of 1/2 of 1% per day for the first 6 days of extra time required, and for the each additional day thereafter, the stipulated penalty is increased by 10% of P35.00 each day. If he pays the total penalty of P6,160, by how many days did he overrun his contract time? O 14 O 12 06 8On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following information pertains to the said contract each customer is to sign. Each house costs 4,000,000 each (a total of 10 houses are to be constructed). Construction will take 2 years to complete. Payment terms are 50% by the end of the 1st year, 25% at the end of the 2nd year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6. Total cost of land- 2,000,000 Estimated total cost of construction - 25,000,000 (including the costs for the common areas, streets and light posts amounting to 5,000,000); Estimated total cost of contract for the 10 houses -…
- On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following data pertains to the said contract each customer is to sign. Each house costs $4,000,000 each (a total of 10 houses are to be constructed). Construction will take 2 years to complete. Payment terms are 50% by the end of the 1st year, 25% at the end of the 2nd year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6. Total cost of land - $2,000,000; Estimated total cost of construction - $25,000,000, (including the costs for the common areas, streets and light posts amounting to $5,000,000); Estimated total cost of contract for the 10 houses -…A contractor failing to complete his contract worth P700,000 in a specified time is compelled to pay the penalty of ½ of 1% per day for the first 6 days of the extra time required, and for each additional day thereafter, the stipulated penalty is increased by 10% each day. If he pays a total penalty of P61,600 by how many days did he overrun his contract time?On January 1, 2016, BUNNY, a real estate company, entered into a contract to construct a subdivision on a piece of land it has acquired and, when construction is complete, to deliver the finished houses to their customers. The following information pertains to the said contract each customer is to sign. Each house costs P4,000,000 each (a total of 10 houses are to be constructed), Construction will take 2 years to complete. Payment terms are 50% by the end of the 1" year, 25% at the end of the 2 year and the balance will be paid after 3 months from the final turn-over. The client can transfer the contract to another, should they not feel satisfied with the house on or before the house is 50% complete. The company incurred the following expenses for 20x6,Total cost of land ~ P2M; Estimated total cost of construction ~ P25M, (including the costs for the common areas, streets and light posts amounting to P5M); Estimated total cost of contract for the 10 houses ~ P40M; In CY 20x6, total…
- Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $184,000. In addition, as part of the contract, a performance bonus of $36,400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,100 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Determine the transaction price that Pina…Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Instructions a. Determine the transaction…You were delayed for 13 days from date of delivery time. A standard liquidated damages (LD) is imposed on you. Compute how much are you going to receive in your final billing if your contract amount is Php 3.5 million.
![Principles of Cost Accounting](https://www.bartleby.com/isbn_cover_images/9781305087408/9781305087408_smallCoverImage.gif)
![Principles of Cost Accounting](https://www.bartleby.com/isbn_cover_images/9781305087408/9781305087408_smallCoverImage.gif)