A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid ₱ 120.00 a day, 25 at ₱ 180.00 a day, and 5 at ₱ 250.00 a day. For each day beyond the original 100 days, the contractor has to pay ₱ 500.00 liquidated damages.

Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter3: Accounting For Labor
Section: Chapter Questions
Problem 15E
icon
Related questions
Question

A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 130 days. Of the 80 men, 50 are each paid ₱ 120.00 a day, 25 at ₱ 180.00 a day, and 5 at ₱ 250.00 a day. For each day beyond the original 100 days, the contractor has to pay ₱ 500.00 liquidated damages.

 

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage