A company produces work boots. The company received and produced an order for 3,300 pairs of boots. The following information is available regarding this order. 6.7 days Process time Inspection time 7.9 days Move time 7.5 days 10.2 days Wait time What is this company's manufacturing cycle efficiency?

icon
Related questions
Question

Give me Answer

A company produces work boots. The company received and
produced an order for 3,300 pairs of boots. The following
information is available regarding this order.
6.7 days
Process time
Inspection time 7.9 days
Move time
7.5 days
10.2 days
Wait time
What is this company's manufacturing cycle efficiency?
Transcribed Image Text:A company produces work boots. The company received and produced an order for 3,300 pairs of boots. The following information is available regarding this order. 6.7 days Process time Inspection time 7.9 days Move time 7.5 days 10.2 days Wait time What is this company's manufacturing cycle efficiency?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer