A 100MW hydro-electric station is supplying full The water is supplied from a reservoir of 1km2 s reduction in the water level of the reservoir in o

icon
Related questions
Question
A 100MW hydro-electric station is supplying full load for 10 hours in a day.
The water is supplied from a reservoir of 1km2 surface area. Calculate the
reduction in the water level of the reservoir in one day. Assume effective
head of water as 200 m and efficiency of the the station is 80%.
Transcribed Image Text:A 100MW hydro-electric station is supplying full load for 10 hours in a day. The water is supplied from a reservoir of 1km2 surface area. Calculate the reduction in the water level of the reservoir in one day. Assume effective head of water as 200 m and efficiency of the the station is 80%.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer