9:24 8 ☑ Answered:... Now! 응 bartleby.com SEARCH ASK Question مه 57% (b) Activity based costing method. 3. XYZ manufactures four products, namely A, B, C and D using the same plant and process. Following information relates to a production period: Labour Product Volume Material Cost per unit Labour per unit Direct Time per unit Machine Cost per unit ₹ ? A 500 5 1/2 hour B 5,000 5 1/2 hour 1/4 hour 1/4 hour 3 3 C 600 D 7,000 16 7 2 hours 1 hour 12 1 1 hours 12 hours 9 Total production overhead recovered by the cost accounting system is analysed under the following headings: Factory overhead applicable to machine-oriented activity 37,425; Set-up costs 4,355; Cost of ordering materials 1,920; Handling materials 7,580; Administration for spare parts 8,600. These overhead costs are absorbed by products on a machine hour rate of 4.60 per hour giving an overhead cost per product of A= 1-20; B=1-20; C=4-80; D=7-20 However, investigation into the production overhead activities for the period reveals the following totals: Number of Period Number of set-ups Number of material orders handled A 1 1 2 B 6 4 10 C 2 1 3 D 8 4 12 17 10 27 Your are required: Number of times Material was spare parts 2 5 1 4 12 to compute an overhead cost per product using activity based costing, tracing overheads to production units by means of cost drivers; and the differences disclosed between overheads traced by the Transcribed Image Text: (b) Activity based čóšting. XYZ manufactures four products, namely A, B, C and D using the same plant and process. Following information relates to a production period : Material Direct Machine Labour Volume Cost per unit Labour per unit Time per unit Cost per unit Product 500 1/2 hour 1/4 hour 5,000 1/2 hour 1/4 hour 3 C 600 16 2 hours 1 hour 12 D 7,000 1 hours 12 hours |||
9:24 8 ☑ Answered:... Now! 응 bartleby.com SEARCH ASK Question مه 57% (b) Activity based costing method. 3. XYZ manufactures four products, namely A, B, C and D using the same plant and process. Following information relates to a production period: Labour Product Volume Material Cost per unit Labour per unit Direct Time per unit Machine Cost per unit ₹ ? A 500 5 1/2 hour B 5,000 5 1/2 hour 1/4 hour 1/4 hour 3 3 C 600 D 7,000 16 7 2 hours 1 hour 12 1 1 hours 12 hours 9 Total production overhead recovered by the cost accounting system is analysed under the following headings: Factory overhead applicable to machine-oriented activity 37,425; Set-up costs 4,355; Cost of ordering materials 1,920; Handling materials 7,580; Administration for spare parts 8,600. These overhead costs are absorbed by products on a machine hour rate of 4.60 per hour giving an overhead cost per product of A= 1-20; B=1-20; C=4-80; D=7-20 However, investigation into the production overhead activities for the period reveals the following totals: Number of Period Number of set-ups Number of material orders handled A 1 1 2 B 6 4 10 C 2 1 3 D 8 4 12 17 10 27 Your are required: Number of times Material was spare parts 2 5 1 4 12 to compute an overhead cost per product using activity based costing, tracing overheads to production units by means of cost drivers; and the differences disclosed between overheads traced by the Transcribed Image Text: (b) Activity based čóšting. XYZ manufactures four products, namely A, B, C and D using the same plant and process. Following information relates to a production period : Material Direct Machine Labour Volume Cost per unit Labour per unit Time per unit Cost per unit Product 500 1/2 hour 1/4 hour 5,000 1/2 hour 1/4 hour 3 C 600 16 2 hours 1 hour 12 D 7,000 1 hours 12 hours |||
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 5PB: Wrappers Tape makes two products: Simple and Removable. It estimates it will produce 369,991 units...
Related questions
Question

Transcribed Image Text:9:24
8 ☑
Answered:...
Now!
응
bartleby.com
SEARCH
ASK
Question
مه
57%
(b) Activity based costing method.
3. XYZ manufactures four products, namely A, B, C and D using the same plant and process.
Following information relates to a production period:
Labour
Product
Volume
Material
Cost per unit Labour per unit
Direct
Time per unit
Machine
Cost per unit
₹
?
A
500
5
1/2 hour
B
5,000
5
1/2 hour
1/4 hour
1/4 hour
3
3
C
600
D
7,000
16
7
2 hours
1 hour
12
1
1
hours
12 hours
9
Total production overhead recovered by the cost accounting system is analysed under the
following headings:
Factory overhead applicable to machine-oriented activity 37,425; Set-up costs 4,355; Cost
of ordering materials 1,920; Handling materials 7,580; Administration for spare parts
8,600.
These overhead costs are absorbed by products on a machine hour rate of 4.60 per hour
giving an overhead cost per product of
A= 1-20; B=1-20; C=4-80; D=7-20
However, investigation into the production overhead activities for the period reveals the
following totals:
Number of
Period
Number of
set-ups
Number of
material
orders
handled
A
1
1
2
B
6
4
10
C
2
1
3
D
8
4
12
17
10
27
Your are required:
Number of times
Material was
spare parts
2
5
1
4
12
to compute an overhead cost per product using activity based costing, tracing
overheads to production units by means of cost drivers; and
the differences disclosed between overheads traced by the
Transcribed Image Text: (b) Activity based čóšting. XYZ
manufactures four products, namely A, B, C and D using
the same plant and process. Following information relates
to a production period : Material Direct Machine Labour
Volume Cost per unit Labour per unit Time per unit Cost
per unit Product 500 1/2 hour 1/4 hour 5,000 1/2 hour 1/4
hour 3 C 600 16 2 hours 1 hour 12 D 7,000 1 hours 12 hours
|||
AI-Generated Solution
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College

Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning

Financial & Managerial Accounting
Accounting
ISBN:
9781337119207
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College

Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning

Financial & Managerial Accounting
Accounting
ISBN:
9781337119207
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning