5. How many system bonding jumpers normally are there for a separately derived system that's grounded? A. Three B. Two C. One D. Zero 6. How many grounded neutral conductors are in a 208Y/120 volt, 3-phase, 4-wire system? A. Three B. Two C. One D. Four 7. Which of the following are sometimes installed as an emergency system, legally required standby system, or optional standby power system for a building or structure? A. Generators B. Surge protection devices C. Surge arresters D. Transformers 8. If the system bonding jumper in a DC system is a screw, what color must the screw be? A. White B. Red C. Orange D. Green 9. If overcurrent protection is provided in the transformer of a separately derived system, which of the following statements is correct? A. An equipment grounding conductor must be run with the conductors between the transformer and the building's disconnect. B. There's no need for service equipment or a panelboard in the separate building. C. A ground electrode must be present at the transformer and the building's disconnect. D. The neutral should be bonded to the equipment grounding conductor at the service equipment in the separate building. 10. A separate building that's supplied with a feeder or branch service will also need a A. neutral conductor bonded to ground. B. separate EGC from the supply EGC. C. grounding electrode system. D. transformer for isolation. 11. An electrical system that's not grounded and is between 120 and 1000 volts must include the use of A. equipotential barriers. B. ground isolators. C. ground detectors. D. arc suppression. 12. Which grounding method is typically required of higher-voltage systems? A. Grounding through inductors B. Grounding through a high-impedance device C. Grounding through surge arresters   D. Grounding through a low amount of resistance 13. Which of the following is suitable as an equipment grounding conductor so long as it does so under more restrictive conditions? A. Flexible metal conduit B. Rigid metal conduit C. Armored cable D. Electrical metallic tubing 14. How many separate equipment grounding paths are required for branch circuits serving patient care spaces? A. One B. Two C. Four D. Three 15. If installed with the feeder to the building or structure, the _______ shall be connected to the building or structure's disconnecting means and to the grounding electrode system. A. supply-side bonding jumper B. load-side bonding jumper C. grounding electrode conductor D. equipment grounding conductor 16. If the first overcurrent protective device isn't located at the generator, a/an _______ bonding jumper must be installed with the feeder up to the first system overcurrent protective device enclosure. A. load-side B. equipment C. main D. supply-side 17. The _______ is typically where the service main bonding jumper is installed or where the system bonding jumper is installed for a separately derived system. A. equipotential plane B. site-isolating device C. isolated power system D. point of grounding 18. An equipotential bonding grid at a farm location is to be connected to the ground terminal bus of the nearest panelboard. Which of the following is the minimum size of solid copper conductor that can be used for this bonding action? A. AWG 12 B. AWG 14 C. AWG 8 D. AWG 10 19. Which of the following is an approved disconnecting means for a feeder or branch circuit supplying a separate building or structure? A. Bonding locknut B. Panelboard C. Circuit breaker D. Overcurrent device 20. One limitation of a high-impedance grounded neutral system is that A. the phase-to-ground voltage can be no greater than 240 volts AC. B. voltage can vary across the supply conductors. C. there can be no neutral to line loads. D. an EGC must be connected to the neutral every 1300 feet.

Introductory Circuit Analysis (13th Edition)
13th Edition
ISBN:9780133923605
Author:Robert L. Boylestad
Publisher:Robert L. Boylestad
Chapter1: Introduction
Section: Chapter Questions
Problem 1P: Visit your local library (at school or home) and describe the extent to which it provides literature...
icon
Related questions
icon
Concept explainers
Question

5. How many system bonding jumpers normally are there for a separately derived system that's grounded? A. Three
B. Two
C. One

D. Zero

6. How many grounded neutral conductors are in a 208Y/120 volt, 3-phase, 4-wire system? A. Three
B. Two
C. One

D. Four

7. Which of the following are sometimes installed as an emergency system, legally required standby system, or optional standby power system for a building or structure?

A. Generators
B. Surge protection devices C. Surge arresters
D. Transformers

8. If the system bonding jumper in a DC system is a screw, what color must the screw be? A. White
B. Red
C. Orange

D. Green

9. If overcurrent protection is provided in the transformer of a separately derived system, which of the following statements is correct?

A. An equipment grounding conductor must be run with the conductors between the transformer and the building's disconnect. B. There's no need for service equipment or a panelboard in the separate building.
C. A ground electrode must be present at the transformer and the building's disconnect.
D. The neutral should be bonded to the equipment grounding conductor at the service equipment in the separate building.

10. A separate building that's supplied with a feeder or branch service will also need a A. neutral conductor bonded to ground.
B. separate EGC from the supply EGC.
C. grounding electrode system.

D. transformer for isolation.

11. An electrical system that's not grounded and is between 120 and 1000 volts must include the use of A. equipotential barriers.
B. ground isolators.
C. ground detectors.

D. arc suppression.

12. Which grounding method is typically required of higher-voltage systems? A. Grounding through inductors
B. Grounding through a high-impedance device
C. Grounding through surge arresters

 

D. Grounding through a low amount of resistance

13. Which of the following is suitable as an equipment grounding conductor so long as it does so under more restrictive conditions?

A. Flexible metal conduit B. Rigid metal conduit
C. Armored cable
D. Electrical metallic tubing

14. How many separate equipment grounding paths are required for branch circuits serving patient care spaces?

A. One B. Two C. Four D. Three

15. If installed with the feeder to the building or structure, the _______ shall be connected to the building or structure's disconnecting means and to the grounding electrode system.

A. supply-side bonding jumper
B. load-side bonding jumper
C. grounding electrode conductor D. equipment grounding conductor

16. If the first overcurrent protective device isn't located at the generator, a/an _______ bonding jumper must be installed with the feeder up to the first system overcurrent protective device enclosure.

A. load-side B. equipment C. main
D. supply-side

17. The _______ is typically where the service main bonding jumper is installed or where the system bonding jumper is installed for a separately derived system.

A. equipotential plane
B. site-isolating device C. isolated power system D. point of grounding

18. An equipotential bonding grid at a farm location is to be connected to the ground terminal bus of the nearest panelboard. Which of the following is the minimum size of solid copper conductor that can be used for this bonding action?

A. AWG 12 B. AWG 14 C. AWG 8 D. AWG 10

19. Which of the following is an approved disconnecting means for a feeder or branch circuit supplying a separate building or structure?

A. Bonding locknut
B. Panelboard
C. Circuit breaker
D. Overcurrent device

20. One limitation of a high-impedance grounded neutral system is that A. the phase-to-ground voltage can be no greater than 240 volts AC.
B. voltage can vary across the supply conductors.
C. there can be no neutral to line loads.

D. an EGC must be connected to the neutral every 1300 feet.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Protection System in Power Plant
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Introductory Circuit Analysis (13th Edition)
Introductory Circuit Analysis (13th Edition)
Electrical Engineering
ISBN:
9780133923605
Author:
Robert L. Boylestad
Publisher:
PEARSON
Delmar's Standard Textbook Of Electricity
Delmar's Standard Textbook Of Electricity
Electrical Engineering
ISBN:
9781337900348
Author:
Stephen L. Herman
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Electrical Engineering
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education
Fundamentals of Electric Circuits
Fundamentals of Electric Circuits
Electrical Engineering
ISBN:
9780078028229
Author:
Charles K Alexander, Matthew Sadiku
Publisher:
McGraw-Hill Education
Electric Circuits. (11th Edition)
Electric Circuits. (11th Edition)
Electrical Engineering
ISBN:
9780134746968
Author:
James W. Nilsson, Susan Riedel
Publisher:
PEARSON
Engineering Electromagnetics
Engineering Electromagnetics
Electrical Engineering
ISBN:
9780078028151
Author:
Hayt, William H. (william Hart), Jr, BUCK, John A.
Publisher:
Mcgraw-hill Education,