5. ( After surveying a construction site, the surveyor produced the following grid below. If you consider 1.0 ft as the proposed elevation that you can cut to. What is the total cut volume (cy) available if you used grid method to calculate the excavation volume? Cut 2.1 ft 30 ft Cut 3.5 ft 30 ft Cut 3.2 ft Cut 1.2 ft 30 ft Cut 4.6 ft

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter4: Measuring Site Work, Excavation, And Piling
Section: Chapter Questions
Problem 8RQ
icon
Related questions
Question
5. (
After surveying a construction site, the surveyor produced the following grid below. If
you consider 1.0 ft as the proposed elevation that you can cut to. What is the total cut volume (cy)
available if you used grid method to calculate the excavation volume?
Cut
2.1 ft
30 ft
Cut
3.5 ft
30 ft
Cut
3.2 ft
Cut
1.2 ft
30 ft
Cut
4.6 ft
Transcribed Image Text:5. ( After surveying a construction site, the surveyor produced the following grid below. If you consider 1.0 ft as the proposed elevation that you can cut to. What is the total cut volume (cy) available if you used grid method to calculate the excavation volume? Cut 2.1 ft 30 ft Cut 3.5 ft 30 ft Cut 3.2 ft Cut 1.2 ft 30 ft Cut 4.6 ft
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Volumes
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,