4. Currently, the three types of fabrics are produced simultaneously in different locations of the fabric plant using similar processes. Process costing methods are used to determine the unit cost of each fabric. Historically, the plant has never fully utilized any of the three processes. The maximum historical utilization of the capacity has been about 50 percent. Juana Sandoval, the fabric plant manager, is confident that the three operations can be consolidated in a way that there would be sufficient capacity to produce all three fabrics while capturing significant savings by reducing labor and overhead costs. In fact, total direct labor and variable overhead costs would be reduced by 25 percent and fixed overhead costs by 50 percent. Production of the three fabrics can be managed by using a batch production approach; however, one problem is that the yarn used for each fabric differs significantly in cost. Conversion activity is the same for each fabric regardless of the type of yarn. The cost accounting manager has assembled the following budgeted annual data for each process that reflects the expected reductions:   Weaving and Pattern Coloring and Bolting Conversion cost $900,000 $570,000 Expected activity (direct labor hours) 60,000 30,000 a. Calculate the conversion rate for each process using direct labor hours (round to whole dollars): Weaving and Pattern Process:  Coloring and Bolting Process:  b. Assume a batch of 400 bolts of FB70 is produced. The cost of yarn requisitioned for the batch is $40,000. The batch used 2,550 direct labor hours in Weaving and Pattern and 1,200 hours in Coloring and Bolting. In Coloring and Bolting, another $10,000 of materials (dyes) were requisitioned for the batch. Calculate the cost per bolt for the production run of 400 bolts (round to the nearest cent).

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 4CE: Larsen, Inc., produces two types of electronic parts and has provided the following data: There are...
icon
Related questions
icon
Concept explainers
Topic Video
Question

4. Currently, the three types of fabrics are produced simultaneously in different locations of the fabric plant using similar processes. Process costing methods are used to determine the unit cost of each fabric. Historically, the plant has never fully utilized any of the three processes. The maximum historical utilization of the capacity has been about 50 percent. Juana Sandoval, the fabric plant manager, is confident that the three operations can be consolidated in a way that there would be sufficient capacity to produce all three fabrics while capturing significant savings by reducing labor and overhead costs. In fact, total direct labor and variable overhead costs would be reduced by 25 percent and fixed overhead costs by 50 percent. Production of the three fabrics can be managed by using a batch production approach; however, one problem is that the yarn used for each fabric differs significantly in cost. Conversion activity is the same for each fabric regardless of the type of yarn. The cost accounting manager has assembled the following budgeted annual data for each process that reflects the expected reductions:

  Weaving and Pattern Coloring and Bolting
Conversion cost $900,000 $570,000
Expected activity (direct labor hours) 60,000 30,000

a. Calculate the conversion rate for each process using direct labor hours (round to whole dollars):

Weaving and Pattern Process: 
Coloring and Bolting Process: 

b. Assume a batch of 400 bolts of FB70 is produced. The cost of yarn requisitioned for the batch is $40,000. The batch used 2,550 direct labor hours in Weaving and Pattern and 1,200 hours in Coloring and Bolting. In Coloring and Bolting, another $10,000 of materials (dyes) were requisitioned for the batch. Calculate the cost per bolt for the production run of 400 bolts (round to the nearest cent).
$

5. In the Coloring and Bolting Department, 400,000 ounces of other materials were purchased and used to produce Fabric FB70's output of the period.

a. Using the proposed standard cost sheet for Fabric FB70, calculate the following variances for the Coloring and Bolting Department (round actual unit costs and prices to three decimal places; round variances to the nearest dollar):

Enter all amounts as positive numbers.

i. Materials price variance (for other materials only)      
 
ii. Materials usage variance (for other materials only)      
 
iii. Labor rate variance      
 
iv. Labor efficiency variance      
 

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning