4. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resource, electrical engineers (EE), and resource, mechanical engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects? Start 0 10 1 EE 2 1 I 0 2 EE 4 03 ME 3 I 4 EE 1 Develop a loading schedule for each resource below. (Figure 8.3) EE ME 2 3 4 5 6 5 ME 6 6 ME 2 Fill in the times below for a resource activity schedule. ID/RES ES LS EF LF SL 1-EE 2-EE 3-ME 4-EE 5-ME 6-ME 7-EE 7 8 9 7 EE 4 10 11 12 Legend ES ID EF SL SL LS DURALF End Resource Schedule

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
4. Given the network plan that follows, compute
the early, late, and slack times. What is the
project duration? Using any approach you
wish (e.g., trial and error), develop a loading
chart for resource, electrical engineers (EE),
and resource, mechanical engineers (ME).
Assume only one of each resource exists.
Given your resource schedule, compute the
early, late, and slack times for your project.
Which activities are now critical? What is the
project duration now? Could something like
this happen in real projects?
Start
0 1
EE
2
0
02
EE
1
0
4
3
ME
3
I
4
EE
2 3 4 5 6
Fill in the times below for a resource activity schedule.
ID/RES ES LS EF LF SL
1-EE
2-EE
3-ME
4-EE
5-ME
6-ME
7-EE
11
Develop a loading schedule for each resource below. (Figure 8.3)
EE
ME
5
ME
6
6
ME
2
7 8 9
7
EE
4
10
11 12
Legend
ES ID EF
SL
SL
LS DURALF
End
Resource
Schedule
Transcribed Image Text:4. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resource, electrical engineers (EE), and resource, mechanical engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects? Start 0 1 EE 2 0 02 EE 1 0 4 3 ME 3 I 4 EE 2 3 4 5 6 Fill in the times below for a resource activity schedule. ID/RES ES LS EF LF SL 1-EE 2-EE 3-ME 4-EE 5-ME 6-ME 7-EE 11 Develop a loading schedule for each resource below. (Figure 8.3) EE ME 5 ME 6 6 ME 2 7 8 9 7 EE 4 10 11 12 Legend ES ID EF SL SL LS DURALF End Resource Schedule
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.