3.2 Consider the time-cost table below and its network. Suppose indirect cost is $1.50 per day. Consider only the direct cost presented in the table below. Perform the time-cost trade-off method and identify all possible alternatives. Normal Crash Normal Crash Activity Time Time Cost Cost Ꭰ A 4 3 10 15 2 B 6 4 C D 9 E F 22 7864 6 985 45 13 12 19 B 13 22 E 3 8 10 F 4.2 Consider exercise 3.2. Only consider the network and the normal times given in exercise 3.2. Use the LP approach to find the project duration. Also, identify earliest times and latest times for all activities and the critical path by using LP.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
3.2 Consider the time-cost table below and its network. Suppose indirect cost is $1.50 per
day. Consider only the direct cost presented in the table below. Perform the time-cost
trade-off method and identify all possible alternatives.
Normal Crash Normal Crash
Activity Time Time Cost Cost
Ꭰ
A
4
3
10
15
2
B
6
4
C
D
9
E
F
22
7864
6
985
45
13
12
19
B
13
22
E
3
8
10
F
4.2 Consider exercise 3.2. Only consider the network and the normal times given in
exercise 3.2. Use the LP approach to find the project duration. Also, identify earliest
times and latest times for all activities and the critical path by using LP.
Transcribed Image Text:3.2 Consider the time-cost table below and its network. Suppose indirect cost is $1.50 per day. Consider only the direct cost presented in the table below. Perform the time-cost trade-off method and identify all possible alternatives. Normal Crash Normal Crash Activity Time Time Cost Cost Ꭰ A 4 3 10 15 2 B 6 4 C D 9 E F 22 7864 6 985 45 13 12 19 B 13 22 E 3 8 10 F 4.2 Consider exercise 3.2. Only consider the network and the normal times given in exercise 3.2. Use the LP approach to find the project duration. Also, identify earliest times and latest times for all activities and the critical path by using LP.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education