3) While undertaking a project evaluation for a wind park of 100MW , you have received a production estimate of 3500 full load hours in the P-50 case. The coefficient of variation for this estimate is 10% . What is the P-75 production (in GWh/year)? A) 238 B) 326 C) 3264 D) 114 E) 586
3) While undertaking a project evaluation for a wind park of 100MW , you have received a production estimate of 3500 full load hours in the P-50 case. The coefficient of variation for this estimate is 10% . What is the P-75 production (in GWh/year)? A) 238 B) 326 C) 3264 D) 114 E) 586
Related questions
Question
N1
3) While undertaking a project evaluation for a wind park of
100MW
, you have received a production estimate of 3500 full load hours in the P-50 case. The coefficient of variation for this estimate is
10%
. What is the P-75 production (in GWh/year)? A) 238 B) 326 C) 3264 D) 114 E) 586
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps