Question
20. In three weeks, six workers can assemble 32 products. Working at the same rate, how many workers are needed to assemble 544 products in the same
amount of time?
115
182
96
102
Transcribed Image Text:20. In three weeks, six workers can assemble 32 products. Working at the same rate, how many workers are needed to assemble 544 products in the same amount of time? 115 182 96 102
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell