2. AG Construction enters into a contract with a customer to build a new headquarters facility for $1,000,000 on January 1, 2023 with a performance bonus of $100,000 if the building is completed by July 31, 2023. The bonus is reduced by $20,000 each week that completion is delayed. AG commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14, 2023 5% August 21, 2023 5% a. Calculate the contract price for AG using the probability-weighted (expected value) method. b. Assume that AG can only determine the probabilities of completing the project by July 31 (65%) or not meeting the deadline (35%). Calculate the contract price under this scenario.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Qw.149.

2. AG Construction enters into a contract with a customer to build a new
headquarters facility for $1,000,000 on January 1, 2023 with a performance
bonus of $100,000 if the building is completed by July 31, 2023. The bonus is
reduced by $20,000 each week that completion is delayed. AG commonly
includes these completion bonuses in its contracts and, based on prior
experience, estimates the following completion outcomes:
Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14,
2023 5% August 21, 2023 5%
a. Calculate the contract price for AG using the probability-weighted
(expected value) method.
b. Assume that AG can only determine the probabilities of completing the
project by July 31 (65%) or not meeting the deadline (35%). Calculate the
contract price under this scenario.
Transcribed Image Text:2. AG Construction enters into a contract with a customer to build a new headquarters facility for $1,000,000 on January 1, 2023 with a performance bonus of $100,000 if the building is completed by July 31, 2023. The bonus is reduced by $20,000 each week that completion is delayed. AG commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14, 2023 5% August 21, 2023 5% a. Calculate the contract price for AG using the probability-weighted (expected value) method. b. Assume that AG can only determine the probabilities of completing the project by July 31 (65%) or not meeting the deadline (35%). Calculate the contract price under this scenario.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education