13. A project consists of four tasks: A, B, C, and D. Task A must be completed before B and C are started, and task C must be completed before task D is started. Each task takes 1 day to complete. 13a) What is the duration of this project in days? esc ock DSIM 350- 14. Given the following diagram showing activities and time, enter the data into the table below and then load into t Project Management spreadsheet (note the times and predecessors). Enter the data into the Project Managemen table and then answer the questions that follow. Name: < ! 1 Q A NE 1 2 N > W S Q # 3 X E D $ 4 C R TASK B 6 weeks F % 5 V T G ^ 6 TASK G 5 weeks TASK E 4 weeks Y B & 7 H U N * CO TASK H 2 weeks 8 J # M ( 9 K ( O о V. < 1 H END ) 0 L D) P command . V - : .... 7₁ { [ option + = 2.1 ? G 11
13. A project consists of four tasks: A, B, C, and D. Task A must be completed before B and C are started, and task C must be completed before task D is started. Each task takes 1 day to complete. 13a) What is the duration of this project in days? esc ock DSIM 350- 14. Given the following diagram showing activities and time, enter the data into the table below and then load into t Project Management spreadsheet (note the times and predecessors). Enter the data into the Project Managemen table and then answer the questions that follow. Name: < ! 1 Q A NE 1 2 N > W S Q # 3 X E D $ 4 C R TASK B 6 weeks F % 5 V T G ^ 6 TASK G 5 weeks TASK E 4 weeks Y B & 7 H U N * CO TASK H 2 weeks 8 J # M ( 9 K ( O о V. < 1 H END ) 0 L D) P command . V - : .... 7₁ { [ option + = 2.1 ? G 11
MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
Related questions
Question
Questions in red 13-14

Transcribed Image Text:13. A project consists of four tasks: A, B, C, and D. Task A must be completed before B and C are started,
and task C must be completed before task D is started. Each task takes 1 day to complete.
13a) What is the duration of this project in days?
esc
ock
Name:
DSIM 350-
14. Given the following diagram showing activities and time, enter the data into the table below and then load into t
Project Management spreadsheet (note the times and predecessors). Enter the data into the Project Managemen
table and then answer the questions that follow.
control
!
1
Q
A
@
NE
2
N
>
W
S
Q
#
3
X
1
option command
E
D
$
4
C
R
TASK B
6 weeks
F
%
5
V
T
G
A
6
TASK G
5 weeks
TASK E
4 weeks
Y
B
&
7
H
U
N
* CO
TASK H
2 weeks
I
8
J
5+
M
(
9
K
(
O
O
<
1
H
END
)
0
L
D)
P
command
A.
-
>
:
...
I
{
[
option
+
=
2.1
?
G
11

Transcribed Image Text:Jacksonville University in Jacksonville, Fla
MYJU Students
Blackboard Learn
14. Given the following diagram showing activities and time, enter the data into the table below and then load into the
Project Management spreadsheet (note the times and predecessors). Enter the data into the Project Management
table and then answer the questions that follow.
I
esc
1
trol
1
Q
A
N
2
W
S
#
3
X
TASK A
1
option command
H
2 weeks
a
E
D
$
4
C
TASK B
R
6 weeks
F
TASK C
4 weeks
TASK D
Activity
a
b
2 weeks
с
d
14a) What steps comprise the "critical path"?
14c) What is the minimum completion time in weeks?
14d) If TASK C can be completed one week sooner for a small fee, would it be worthwhile to pay for it?
e
f
g
h
1-prod-feet01-xythos.content.blackboardcdn.com
%
5
T
G
TASK G
^
6
5 weeks
TASK E
Predecessor
V B
4 weeks
TASK F
3 weeks
Y
N
7
H
Duration (weeks)
U
N
* CO
TASK H
8
2 weeks
J
1
M
(
9
K
-O
0
<
END
I
)
0
L
command
P
Bhttps:/learn-us-east-1-prod-fleet01-xythos.conte
>
:
;
I
{
option
[
+ 11
=
O
11
?
1
}
1
delete
1
\
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 4 images

Recommended textbooks for you

MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc

Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning

Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning

MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc

Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning

Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning

Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON

The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman

Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman