12:23 Ill 5G Problem 1 The following table gives expected times and variances for a probabilistic duration type of project (we are not given and we don't need the optimistic, most likely, and pessimistic time estimates). Activity Expected Time Variance A 4 0.44 B 3 0.69 C 7 2.25 D 11 2.25 E 4 0.11 F 9 1.36 G 6 0.44 H 6 0.69 I 7 1.36 J 13 1.00 K 3 0.44 12:23 Ill 5G Given the project network below, find the early start (ES), Early Finish (EF). Late Start (LS) and Late Finish (LF) time indices, for the network show below. Use the "expected time" for the critical path method. D A E B F K START FINISH C G H J

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Which is the critical path? O A-D-K O A-E-I-K O A-F-I-K O B-F-I-K O C-G-I-K O C-H-J-K
12:23
Ill 5G
Problem 1
The following table gives expected times and variances for a probabilistic
duration type of project (we are not given and we don't need the optimistic,
most likely, and pessimistic time estimates).
Activity
Expected
Time
Variance
A
4
0.44
B
3
0.69
C
7
2.25
D
11
2.25
E
4
0.11
F
9
1.36
G
6
0.44
H
6
0.69
I
7
1.36
J
13
1.00
K
3
0.44
Transcribed Image Text:12:23 Ill 5G Problem 1 The following table gives expected times and variances for a probabilistic duration type of project (we are not given and we don't need the optimistic, most likely, and pessimistic time estimates). Activity Expected Time Variance A 4 0.44 B 3 0.69 C 7 2.25 D 11 2.25 E 4 0.11 F 9 1.36 G 6 0.44 H 6 0.69 I 7 1.36 J 13 1.00 K 3 0.44
12:23
Ill 5G
Given the project network below, find the early start (ES), Early Finish (EF).
Late Start (LS) and Late Finish (LF) time indices, for the network show below.
Use the "expected time" for the critical path method.
D
A
E
B
F
K
START
FINISH
C
G
H
J
Transcribed Image Text:12:23 Ill 5G Given the project network below, find the early start (ES), Early Finish (EF). Late Start (LS) and Late Finish (LF) time indices, for the network show below. Use the "expected time" for the critical path method. D A E B F K START FINISH C G H J
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.