1. To remedy the traffic situation at a busy intersection in San Fernando City, two plans are being considered. Plan A is to build a complete clover-leaf costing P9,200,000 which would provide for all needs during the next 30 years. Maintenance costs are estimated to be P24,000 a year for the first 15 years and P42,000 a year for the second 15 years. Plan B is to build a partial clover-leaf at a cost of P6,500,000 which would be sufficient for the next 15 years. At the end of 15 years, the clover-leaf will be completed at an estimated cost of P7,500,000. Maintenance would cost P16,800 a year during the first 15 years and P36,000 a year for the second 15 years. If money is worth 18%, which of the two plans would you recommend?

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

Show solution

1.
To remedy the traffic situation at a busy intersection in San Fernando City, two plans are being
considered. Plan A is to build a complete clover-leaf costing P9,200,000 which would provide for all needs
during the next 30 years. Maintenance costs are estimated to be P24,000 a year for the first 15 years and
P42,000 a year for the second 15 years. Plan B is to build a partial clover-leaf at a cost of P6,500,000 which
would be sufficient for the next 15 years. At the end of 15 years, the clover-leaf will be completed at an
estimated cost of P7,500,000. Maintenance would cost P16,800 a year during the first 15 years and P36,000
a year for the second 15 years. If money is worth 18%, which of the two plans would you recommend?
Transcribed Image Text:1. To remedy the traffic situation at a busy intersection in San Fernando City, two plans are being considered. Plan A is to build a complete clover-leaf costing P9,200,000 which would provide for all needs during the next 30 years. Maintenance costs are estimated to be P24,000 a year for the first 15 years and P42,000 a year for the second 15 years. Plan B is to build a partial clover-leaf at a cost of P6,500,000 which would be sufficient for the next 15 years. At the end of 15 years, the clover-leaf will be completed at an estimated cost of P7,500,000. Maintenance would cost P16,800 a year during the first 15 years and P36,000 a year for the second 15 years. If money is worth 18%, which of the two plans would you recommend?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Private Information about Consumer Type
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education