1. Organize the information above in an activity precedence table showing the activity, precedent, and duration (calculated using the PERT weighted average formula and round to the nearest integer). 2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 3. Identify the project's critical paths and their lengths.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Please assist in answering this
Three-point duration estimates:
Activity
Optimistic
Most likely
Pessimistic
Duration
A
24
12
18
15
B
12
17
22
17
16
13
16
14
D
7
14
21
14
8
16
18
15
F
13
11
15
12
G
17
13
11
H
16
11
12
12
7
8
9
8.0
J
4
6
7
The dependencies between the 10 activities listed in the table above are as follows:
The project starts with three activities-A and B-which can be done concurrently
When Activity A and Activity B are finished, Activity C can start
When Activity B is finished, Activity D can start
When Activity B is finished, Activity E can start
• When Activity C and Activity D are finished, Activity F can start
When Activity D is finished, Activity G can start
When Activity F is finished, Activity H can start
When Activity F and Activity G are finished, Activity I can start
When Activity E and Activity G are finished, Activity J can start
The project is complete when activity H, I and J are finished
Instructions:
1. Organize the information above in an activity precedence table showing the activity,
precedent, and duration (calculated using the PERT weighted average formula and
round to the nearest integer).
2. Draw an AON network diagram and calculate its early start, early finish, late start and
late finish times, floats (Free and total) for each activity. Make sure you fully label all
nodes in the network.
3. Identify the project's critical paths and their lengths.
Transcribed Image Text:Three-point duration estimates: Activity Optimistic Most likely Pessimistic Duration A 24 12 18 15 B 12 17 22 17 16 13 16 14 D 7 14 21 14 8 16 18 15 F 13 11 15 12 G 17 13 11 H 16 11 12 12 7 8 9 8.0 J 4 6 7 The dependencies between the 10 activities listed in the table above are as follows: The project starts with three activities-A and B-which can be done concurrently When Activity A and Activity B are finished, Activity C can start When Activity B is finished, Activity D can start When Activity B is finished, Activity E can start • When Activity C and Activity D are finished, Activity F can start When Activity D is finished, Activity G can start When Activity F is finished, Activity H can start When Activity F and Activity G are finished, Activity I can start When Activity E and Activity G are finished, Activity J can start The project is complete when activity H, I and J are finished Instructions: 1. Organize the information above in an activity precedence table showing the activity, precedent, and duration (calculated using the PERT weighted average formula and round to the nearest integer). 2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 3. Identify the project's critical paths and their lengths.
Expert Solution
Step 1

Below is the solution:- 

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.