1. Latest Deadline First (LDF) Given the precedence graph in Figure 1 and the following table of task execution times and deadlines, determine the Latest Deadline First (LDF) schedule. C₁ Di J₁ J2 J3 J4 J5 J6 J7 J8 3 3 3 2 2 1 15 12 18 19 20 35 48 4 2 8 11

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question
### Latest Deadline First (LDF) Scheduling

**Objective:**
Given the precedence graph and the following table of task execution times and deadlines, determine the Latest Deadline First (LDF) schedule.

**Table of Task Execution Times and Deadlines:**

| Task (Ji) | J1 | J2 | J3 | J4 | J5 | J6 | J7 | J8 |
|-----------|----|----|----|----|----|----|----|----|
| Execution Time (Ci) | 3 | 4 | 2 | 3 | 3 | 2 | 1 | 1 |
| Deadline (Di)       | 5 | 8 | 11 | 15 | 12 | 18 | 19 | 20 |

**Figure 1: Task Precedence Graph**

The precedence graph indicates the order in which tasks must be performed, visualized as a directed graph where each node represents a task and directed edges indicate precedence constraints. 

**Explanation of the Graph:**

- The graph consists of 8 circular nodes labeled from \(J_1\) to \(J_8\).
- Arrows (directed edges) connect these nodes, indicating the dependencies between tasks.
- If there is a directed edge from node \(J_i\) to node \(J_j\), task \(J_j\) cannot start until task \(J_i\) is completed.

The goal is to create a schedule where tasks are arranged according to their deadlines, ensuring that all precedence constraints are satisfied and tasks are executed as late as possible without violating their respective deadlines.

Instructions for determining the LDF schedule:
1. **Identify Deadlines:** Extract deadlines from the given table.
2. **Sort by Deadlines:** Arrange the tasks in decreasing order of deadlines.
3. **Check Precedence Constraints:** Ensure that all preceding tasks (based on the graph) are scheduled before their dependent tasks.
4. **Formulate Schedule:** Allocate execution times in a sequence that respects the precedence constraints and minimizes the slack time before deadlines.

By following the principles of the LDF scheduling algorithm, we can effectively manage task sequencing in complex systems with interdependent activities.
Transcribed Image Text:### Latest Deadline First (LDF) Scheduling **Objective:** Given the precedence graph and the following table of task execution times and deadlines, determine the Latest Deadline First (LDF) schedule. **Table of Task Execution Times and Deadlines:** | Task (Ji) | J1 | J2 | J3 | J4 | J5 | J6 | J7 | J8 | |-----------|----|----|----|----|----|----|----|----| | Execution Time (Ci) | 3 | 4 | 2 | 3 | 3 | 2 | 1 | 1 | | Deadline (Di) | 5 | 8 | 11 | 15 | 12 | 18 | 19 | 20 | **Figure 1: Task Precedence Graph** The precedence graph indicates the order in which tasks must be performed, visualized as a directed graph where each node represents a task and directed edges indicate precedence constraints. **Explanation of the Graph:** - The graph consists of 8 circular nodes labeled from \(J_1\) to \(J_8\). - Arrows (directed edges) connect these nodes, indicating the dependencies between tasks. - If there is a directed edge from node \(J_i\) to node \(J_j\), task \(J_j\) cannot start until task \(J_i\) is completed. The goal is to create a schedule where tasks are arranged according to their deadlines, ensuring that all precedence constraints are satisfied and tasks are executed as late as possible without violating their respective deadlines. Instructions for determining the LDF schedule: 1. **Identify Deadlines:** Extract deadlines from the given table. 2. **Sort by Deadlines:** Arrange the tasks in decreasing order of deadlines. 3. **Check Precedence Constraints:** Ensure that all preceding tasks (based on the graph) are scheduled before their dependent tasks. 4. **Formulate Schedule:** Allocate execution times in a sequence that respects the precedence constraints and minimizes the slack time before deadlines. By following the principles of the LDF scheduling algorithm, we can effectively manage task sequencing in complex systems with interdependent activities.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY