1. Given below is the list of activities with respective durations of a single- storey residential project, make a logical arrangement of activities by filling out the column for Predecessor Activities. 2. Construct a Network Diagram. 3. What is the project duration if no delays will occur? 4. What are the activities in the Critical Path? 5. What is the Early Start and Early Finish of each activity? 6. What is the Late Start and late Finish of each activity? Activities Duration Predecessors 1. Clearing and Grabbing 3 DAYS 2. Excavation 9 DAYS 3. Soil Poisoning 3 DAYS 4. Rebar Works 30 DAYS 5. Concreting 24 DAYS 6. Backfilling 9 DAYS 7. Forms and Scaffolding 36 DAYS 8. CHB laying 24 DAYS 9. Carpentry 24 DAYS 10. Roofing 12 DAYS 11. Tiles Installation 6 DAYS 12. Hardwares 3 DAYS 13. Plumbing 24 DAYS 14. Electrical 27 DAYS 15. Painting 6 DAYS

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Hi there! Would you mind if i ask you (expert) again to help me in my assignment. Just like the other time, its about making network diagram and other stuff relating to it. I kinda have difficulties in understanding it so would you consider me this time. Please help me out of it. Hoping for your kind consideration thankyou!

 

Anyways, in the given image below, thats my assignment. Hope you did it well and taught me about it. Thanks a lot. 

 

Have a good day and blessed u more!

12:54 M &
30 79%
LP2 in CE 7_.docx.pdf
16
LEARNING PACKET 2 Construction Methods and Project Management
1.2.5 Assessment
Summative Test 3
In a separate sheet of paper answer the following (hand-written):
1. Given below is the list of activities with respective durations of a single-
storey residential project, make a logical arrangement of activities by
filling out the column for Predecessor Activities.
2. Construct a Network Diagram.
3. What is the project duration if no delays will occur?
4. What are the activities in the Critical Path?
5. What is the Early Start and Early Finish of each activity?
6. What is the Late Start and late Finish of each activity?
Activities
Duration
Predecessors
1. Clearing and Grabbing
3 DAYS
2. Excavation
9 DAYS
3. Soil Poisoning
3 DAYS
4. Rebar Works
30 DAYS
5. Concreting
24 DAYS
6. Backfilling
9 DAYS
7. Forms and Scaffolding
36 DAYS
8. CHB laying
24 DAYS
9. Carpentry
| 24 DAYS
10. Roofing
12 DAYS
11. Tiles Installation
6 DAYS
12. Hardwares
3 DAYS
13. Plumbing
24 DAYS
14. Electrical
27 DAYS
15. Painting
6 DAYS
17
LEARNING PACKET 2 Construction Methods and Project Management
UNIT 2: CONSTRUCTION ESTIMATE AND VALUES
ENGINEERING
2.0 INTENDED LEARNING OUTCOMES
At the end of this learning packet you will be able to distinguish the pros
and cons of rent-lease-buv decision and discuss the different ohiectives of
II
Transcribed Image Text:12:54 M & 30 79% LP2 in CE 7_.docx.pdf 16 LEARNING PACKET 2 Construction Methods and Project Management 1.2.5 Assessment Summative Test 3 In a separate sheet of paper answer the following (hand-written): 1. Given below is the list of activities with respective durations of a single- storey residential project, make a logical arrangement of activities by filling out the column for Predecessor Activities. 2. Construct a Network Diagram. 3. What is the project duration if no delays will occur? 4. What are the activities in the Critical Path? 5. What is the Early Start and Early Finish of each activity? 6. What is the Late Start and late Finish of each activity? Activities Duration Predecessors 1. Clearing and Grabbing 3 DAYS 2. Excavation 9 DAYS 3. Soil Poisoning 3 DAYS 4. Rebar Works 30 DAYS 5. Concreting 24 DAYS 6. Backfilling 9 DAYS 7. Forms and Scaffolding 36 DAYS 8. CHB laying 24 DAYS 9. Carpentry | 24 DAYS 10. Roofing 12 DAYS 11. Tiles Installation 6 DAYS 12. Hardwares 3 DAYS 13. Plumbing 24 DAYS 14. Electrical 27 DAYS 15. Painting 6 DAYS 17 LEARNING PACKET 2 Construction Methods and Project Management UNIT 2: CONSTRUCTION ESTIMATE AND VALUES ENGINEERING 2.0 INTENDED LEARNING OUTCOMES At the end of this learning packet you will be able to distinguish the pros and cons of rent-lease-buv decision and discuss the different ohiectives of II
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Team Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning