1. Develop a product structure tree for the Mirage tent. 2. Complete a MRP record for P2.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Problem one
Camper's World is a company that produces camping and other sporting equipment. The company wishes to implement an MRP system for one of its products, the "Mirage" foldable light-weight tent. The
master production schedule (MPS) for this product for the next 12 weeks is given in Table 1 below.
Table 1: MPS for the Mirage tent
Week 1 2 3 4 5 6 7 8 9
MPS
The planned production in week 9 of the MPS is given as 232.
The Mirage tent is assembled from two sub-assemblies: S1 and S2. Sub-assembly S1 requires components C1 and C3, while sub-assembly S2 requires components C2 and part P2. Component C1 is made
from parts Pland P2. The beginning inventory, lot-sizing rule, lead time and usage for all of the items needed to assemble the Mirage tent are given in Table 2.
Assignment Tasks:
Mirage 30
120
1. Develop a product structure tree for the Mirage tent.
2. Complete a MRP record for P2.
Table 2: Mirage Tent
S1
Item Beginning Inventory Lot sizing Rule Usage
S2
C1
C2
C3
P1
P2
0
650
318
0
10
233 232 245 175 135
-
850
0
L4L
L4L
L4L
L4L
L4L
L4L
L4L
11
L4L
1
1
4
3
2
12
8
5 for S2
3 for C1
Lead Time
(weeks)
1
2
1
2
2
3
1
2
Transcribed Image Text:Problem one Camper's World is a company that produces camping and other sporting equipment. The company wishes to implement an MRP system for one of its products, the "Mirage" foldable light-weight tent. The master production schedule (MPS) for this product for the next 12 weeks is given in Table 1 below. Table 1: MPS for the Mirage tent Week 1 2 3 4 5 6 7 8 9 MPS The planned production in week 9 of the MPS is given as 232. The Mirage tent is assembled from two sub-assemblies: S1 and S2. Sub-assembly S1 requires components C1 and C3, while sub-assembly S2 requires components C2 and part P2. Component C1 is made from parts Pland P2. The beginning inventory, lot-sizing rule, lead time and usage for all of the items needed to assemble the Mirage tent are given in Table 2. Assignment Tasks: Mirage 30 120 1. Develop a product structure tree for the Mirage tent. 2. Complete a MRP record for P2. Table 2: Mirage Tent S1 Item Beginning Inventory Lot sizing Rule Usage S2 C1 C2 C3 P1 P2 0 650 318 0 10 233 232 245 175 135 - 850 0 L4L L4L L4L L4L L4L L4L L4L 11 L4L 1 1 4 3 2 12 8 5 for S2 3 for C1 Lead Time (weeks) 1 2 1 2 2 3 1 2
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Documentation techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education