1. A water supply dam will cost $7 million to build and it will have erosion control costs of $800,000 every 5 years forever. At an interest rate of 10% per year, what is the capitalized cost of the dam?

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question

Complete solutions

+Questions:
1. A water supply dam will cost $7 million to build and it will have erosion
control costs of $800,000 every 5 years forever. At an interest rate of 10%
per year, what is the capitalized cost of the dam?
2. A small flood control project has a capital investment cost of $300,000 and
an annual maintenance cost of $80,000 at 10% per year in 5 years. What is
the capitalize cost?
Transcribed Image Text:+Questions: 1. A water supply dam will cost $7 million to build and it will have erosion control costs of $800,000 every 5 years forever. At an interest rate of 10% per year, what is the capitalized cost of the dam? 2. A small flood control project has a capital investment cost of $300,000 and an annual maintenance cost of $80,000 at 10% per year in 5 years. What is the capitalize cost?
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning