1 2 Continued from Problem 1 for Kimpel Products, you were told that the project should be completed in 15 weeks. However, the job times used previously were just updated with the newer information. The newer information offers estimated job times in different situations (optimistic, pessimistic and most likely situations, see Table 2). 234567892: 10 What is the probability that everything will be done in 15 weeks? Show your analysis & calculations using the PERT approach. 11 Table 2 Immediate TIME ESTIMATES (WEEKS) Show your analysis and calculations. Probability 12 Job label predecessor(s) Optimistic Most likely Pessimistic 13 A 1.5 2 3 14 B 1 2 5 15 с 16 17 18 19 ABCR CDEFG 4 5 9 3 6 7 В 5 7 9 с 4 5 8 D, E 3 4 5 20 21

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Please help solve if the critical path is adg (14 weeks)

1
2 Continued from Problem 1 for Kimpel Products, you were told that the project should be completed in 15 weeks. However, the job times used previously were just updated with the newer information. The
newer information offers estimated job times in different situations (optimistic, pessimistic and most likely situations, see Table 2).
234567892:
10
What is the probability that everything will be done in 15 weeks? Show your analysis & calculations using the PERT approach.
11 Table 2
Immediate
TIME ESTIMATES (WEEKS)
Show your analysis
and calculations.
Probability
12 Job label predecessor(s) Optimistic Most likely Pessimistic
13
A
1.5
2
3
14
B
1
2
5
15
с
16
17
18
19
ABCR
CDEFG
4
5
9
3
6
7
В
5
7
9
с
4
5
8
D, E
3
4
5
20
21
Transcribed Image Text:1 2 Continued from Problem 1 for Kimpel Products, you were told that the project should be completed in 15 weeks. However, the job times used previously were just updated with the newer information. The newer information offers estimated job times in different situations (optimistic, pessimistic and most likely situations, see Table 2). 234567892: 10 What is the probability that everything will be done in 15 weeks? Show your analysis & calculations using the PERT approach. 11 Table 2 Immediate TIME ESTIMATES (WEEKS) Show your analysis and calculations. Probability 12 Job label predecessor(s) Optimistic Most likely Pessimistic 13 A 1.5 2 3 14 B 1 2 5 15 с 16 17 18 19 ABCR CDEFG 4 5 9 3 6 7 В 5 7 9 с 4 5 8 D, E 3 4 5 20 21
Expert Solution
steps

Step by step

Solved in 2 steps with 9 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.