1 2 3 Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchen. The jobs necessary to build an experimental model such as research, design, engineering drawings, production, etc. are labelled as A through G. Table 1 shows the data required for this problem. The job can start at the same week when its immediate predecessor(s) is (are) 4 completed. Answer the following questions, Q1 & Q2. 5 6 Q1: Draw the AON graph for this project. Without any crashing, what is the minimum number of weeks to complete this project (i.e., the quickest way to finish the project)? 7 8 9 10 Table 1 The AON graph (Use the shapes of circle and directed arrow provided by Excel by going to "Insert" and then "Shapes") Job label Job description Immediate predecessor(s) 24 25 26 27 28 29 30 31 EN2222222222222≈≈≈33 34 11 Normal time (weeks) Crash time Normal (weeks) cost ($) Crash cost ($) Minimum no. of weeks to complete the project 12 A Market Research 3 2 1,000 1,100 13 B Concept Design 2 1 2,000 2,700 14 C Engineering Drawings -- 5 5 300 300 15 D Prototype Development A 7 4 1,300 1,675 Explain how you find the answer. You cannot get points by just showing a correct number. 16 E Testing and Evaluation B 6 3 850 1,300 17 F Production Planning C 5 4 4,000 4,500 18 G Marketing Strategy D, E 4 2 1,500 2,300 19 20 21 Q2: You are thinking about shortening (i.e. crashing) the entire project. You were just provided with a fund of $1,800 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as possible within $1,800. If there are multiple ways that crash the project to the same project time, you should choose the way that leaves you the most amount of unusable fund. Show your method of crashing the project. Project time after making the best 35 36 37 38 39 40 41 42 Show how you crash the project. Total crashing cost use of $1,800 for crashing weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

Please walk me step by step to help solve this

1
2
3
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchen. The jobs necessary to build an experimental model such as
research, design, engineering drawings, production, etc. are labelled as A through G. Table 1 shows the data required for this problem. The job can start at the same week when its immediate predecessor(s) is (are)
4 completed. Answer the following questions, Q1 & Q2.
5
6
Q1: Draw the AON graph for this project. Without any crashing, what is the minimum number of weeks to complete this project (i.e., the quickest way to finish the project)?
7
8
9
10 Table 1
The AON graph (Use the
shapes of circle and directed
arrow provided by Excel by
going to "Insert" and then
"Shapes")
Job label
Job description
Immediate
predecessor(s)
24
25
26
27
28
29
30
31
EN2222222222222≈≈≈33
34
11
Normal
time
(weeks)
Crash time
Normal
(weeks)
cost ($)
Crash cost
($)
Minimum no. of
weeks to complete
the project
12
A
Market Research
3
2
1,000
1,100
13
B
Concept Design
2
1
2,000
2,700
14
C
Engineering Drawings
--
5
5
300
300
15
D
Prototype Development
A
7
4
1,300
1,675
Explain how you find the answer.
You cannot get points by just
showing a correct number.
16
E
Testing and Evaluation
B
6
3
850
1,300
17
F
Production Planning
C
5
4
4,000
4,500
18
G
Marketing Strategy
D, E
4
2
1,500
2,300
19
20
21
Q2: You are thinking about shortening (i.e. crashing) the entire project. You were just provided with a fund of $1,800 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as
possible within $1,800. If there are multiple ways that crash the project to the same project time, you should choose the way that leaves you the most amount of unusable fund. Show your method of crashing the project.
Project time after
making the best
35
36
37
38
39
40
41
42
Show how you
crash the project.
Total
crashing
cost
use of $1,800 for
crashing
weeks
Transcribed Image Text:1 2 3 Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchen. The jobs necessary to build an experimental model such as research, design, engineering drawings, production, etc. are labelled as A through G. Table 1 shows the data required for this problem. The job can start at the same week when its immediate predecessor(s) is (are) 4 completed. Answer the following questions, Q1 & Q2. 5 6 Q1: Draw the AON graph for this project. Without any crashing, what is the minimum number of weeks to complete this project (i.e., the quickest way to finish the project)? 7 8 9 10 Table 1 The AON graph (Use the shapes of circle and directed arrow provided by Excel by going to "Insert" and then "Shapes") Job label Job description Immediate predecessor(s) 24 25 26 27 28 29 30 31 EN2222222222222≈≈≈33 34 11 Normal time (weeks) Crash time Normal (weeks) cost ($) Crash cost ($) Minimum no. of weeks to complete the project 12 A Market Research 3 2 1,000 1,100 13 B Concept Design 2 1 2,000 2,700 14 C Engineering Drawings -- 5 5 300 300 15 D Prototype Development A 7 4 1,300 1,675 Explain how you find the answer. You cannot get points by just showing a correct number. 16 E Testing and Evaluation B 6 3 850 1,300 17 F Production Planning C 5 4 4,000 4,500 18 G Marketing Strategy D, E 4 2 1,500 2,300 19 20 21 Q2: You are thinking about shortening (i.e. crashing) the entire project. You were just provided with a fund of $1,800 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as possible within $1,800. If there are multiple ways that crash the project to the same project time, you should choose the way that leaves you the most amount of unusable fund. Show your method of crashing the project. Project time after making the best 35 36 37 38 39 40 41 42 Show how you crash the project. Total crashing cost use of $1,800 for crashing weeks
Expert Solution
steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,